ITAC Assessment: WI0062
ITAC logo
ITAC Assessment: WI0062
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product STAINLESS STEEL TANKS
NAICS
n/a
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area
n/a
Annual Production 600
pieces
Production Hrs. Annual 4,375
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $108,472 1,989,449
kWh
Natural Gas $35,885 7,057
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,514 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,364

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.8113: Purchase gas directly from a contract gas supplier $12,224 - - $12,224
-
MMBtu
-
02 2.7261: Install timers and/or thermostats $4,059 $3,500 - $4,059
-
MMBtu
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $709 $2,290 $709
12,896
kWh
- -
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $3,647 - $4,327
-
kWh
- $(-680.0)
05 2.7447: Install vinyl strip / high speed / air curtain doors $1,596 $6,000 - $1,596
-
MMBtu
-
06 2.4312: Improve lubrication practices $1,320 - $1,320
24,326
kWh
- -
07 2.7494: Install storm windows and doors $959 $2,090 - $959
-
MMBtu
-
TOTAL RECOMMENDED $24,514 $13,880 $6,356
37,222
kWh
$18,838
-
MMBtu
$(-680.0)
TOTAL IMPLEMENTED $6,364 $11,790 $709
12,896
kWh
$5,655
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs