| Assessment Year | 1989 |
|---|---|
| Principal Product | ADHESIVES AND PAINTS |
| NAICS |
n/a
|
| SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $160,298 | 2,111,079 |
kWh
|
$0.076 |
| Natural Gas | $68,686 | 15,982 |
MMBtu
|
$4.30 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $33,586 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $12,079 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $15,484 | - |
$17,084
-
kWh
|
- | $(-1,600.0) | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,062 | $5,890 |
$2,062
27,257
kWh
|
- | - | |
| 03 | 2.3132: Recharge batteries on during off-peak demand periods | $4,969 | - |
$4,969
-
kWh
|
- | - | |
| 04 | 2.4312: Improve lubrication practices | $3,869 | - |
$3,869
50,996
kWh
|
- | - | |
| 05 | 2.2437: Recover waste heat from equipment | $2,896 | $3,000 | - |
$2,896
-
MMBtu
|
- | |
| 06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,572 | $2,100 | - |
$1,572
-
MMBtu
|
- | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $1,341 | $3,000 |
$1,341
17,585
kWh
|
- | - | |
| 08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $811 | $500 | - |
$861
-
MMBtu
|
$(-50.0) | |
| 09 | 2.7494: Install storm windows and doors | $582 | $1,276 | - |
$582
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $33,586 | $15,766 |
$29,325
95,838
kWh
|
$5,911
-
MMBtu
|
$(-1,650.0) | ||
| TOTAL IMPLEMENTED | $12,079 | $12,390 |
$8,372
44,842
kWh
|
$3,757
-
MMBtu
|
$(-50.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs