ITAC Assessment: WI0017
ITAC logo
ITAC Assessment: WI0017
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product COUPLERS, WRENCHES, ETC.
NAICS
n/a
SIC 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 95
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 2,125
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $74,864 879,836
kWh
Natural Gas $35,050 7,333
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,791 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,061

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4312: Improve lubrication practices $230 - $230
2,638
kWh
- -
02 2.4221: Install compressor air intakes in coolest locations $336 $956 $336
4,103
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,124 $2,325 $2,124
24,912
kWh
- -
04 2.7447: Install vinyl strip / high speed / air curtain doors $1,290 $1,500 - $1,290
-
MMBtu
-
05 2.8113: Purchase gas directly from a contract gas supplier $10,059 - - $10,059
-
MMBtu
-
06 2.1233: Analyze flue gas for proper air/fuel ratio $371 $500 - $471
-
MMBtu
$(-100.0)
07 2.7226: Use computer programs to optimize hvac performance $4,381 $3,000 $4,381
51,583
kWh
- -
TOTAL RECOMMENDED $18,791 $8,281 $7,071
83,236
kWh
$11,820
-
MMBtu
$(-100.0)
TOTAL IMPLEMENTED $3,061 $3,781 $2,690
31,653
kWh
$471
-
MMBtu
$(-100.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs