ITAC Assessment: UW2220
ITAC logo
ITAC Assessment: UW2220
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Aircraft Manufacturing
NAICS 336411: Aircraft Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 600
Plant Area 94,280
ft2
Annual Production 1,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $137,819 1,588,018
kWh
Electricity Demand $1,895 535
kW-mo/yr
Electricity Fees $10,199 -
Natural Gas $11,014 1,048
MMBtu
TOTAL YEARLY COSTS $160,927
RECOMMENDED SAVINGS* $110,660 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,594

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7261: Install timers and/or thermostats $1,980 $800 $1,723
19,850
kWh
$257
-
kW-mo/yr
02 2.7142: Utilize higher efficiency lamps and/or ballasts $11,653 $33,398 $9,563
110,183
kWh
$2,090
-
kW-mo/yr
03 2.7135: Install occupancy sensors $2,961 $1,423 $2,577
29,696
kWh
$384
-
kW-mo/yr
04 2.9114: Use solar heat to make electricty $94,066 $513,443 $89,089
1,026,366
kWh
$4,977
-
kW-mo/yr
TOTAL RECOMMENDED $110,660 $549,065 $102,952
1,186,095
kWh
$7,708
-
kW-mo/yr
TOTAL IMPLEMENTED $16,594 $35,622 $13,863
159,729
kWh
$2,731
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs