Assessment Year | 1993 |
---|---|
Principal Product | Brazing and Welding Shop |
NAICS |
n/a
|
SIC | 3724: Aircraft Engines and Engine Parts |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
95,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,300
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $278,650 | 5,100,821 |
kWh
|
$0.055 |
Natural Gas | $24,143 | 5,169 |
MMBtu
|
$4.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $33,027 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,808 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.8123: Pay utility bills on time | $2,100 | - |
$2,100
-
kWh
|
|
02 | 2.3191: Use demand controller or load shedder | $20,700 | $20,000 |
$20,700
-
kWh
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,246 | $14,248 |
$3,246
-
kWh
|
|
04 | 2.6232: Install set-back timers | $1,773 | $500 |
$1,773
75,029
kWh
|
|
05 | 2.6232: Install set-back timers | $1,689 | $1,500 |
$1,689
19,930
kWh
|
|
06 | 2.3191: Use demand controller or load shedder | $3,519 | - |
$3,519
-
kWh
|
|
TOTAL RECOMMENDED | $33,027 | $36,248 |
$33,027
94,959
kWh
|
||
TOTAL IMPLEMENTED | $8,808 | $16,248 |
$8,808
94,959
kWh
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs