Assessment Year | 2007 |
---|---|
Principal Product | Aluminum cans |
NAICS | 332431: Metal Can Manufacturing |
SIC | 3411: Metal Cans |
Sales Range | $50 M to 100M |
# of Employees | 109 |
Plant Area |
180,000
ft2
|
Annual Production | 1,800,000,000
pieces
|
Production Hrs. Annual | 8,640
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,127,837 | 21,663,600 |
kWh
|
$0.052 |
Electricity Demand | $211,746 | 36,048 |
kW-mo/yr
|
$5.87 |
Electricity Fees | $11,416 | - |
|
- |
Natural Gas | $866,333 | 78,076 |
MMBtu
|
$11.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $176,769 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,402 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4226: Use / purchase optimum sized compressor | $93,799 | $136,650 |
$81,034
1,460,071
kWh
|
$12,765
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $27,889 | $1,720 |
$28,640
516,031
kWh
|
$4,449
-
kW-mo/yr
|
- | - | $(-5,200.0) | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $28,369 | $138,420 |
$24,556
442,443
kWh
|
$3,813
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,031 | $7,140 |
$3,689
66,469
kWh
|
$557
-
kW-mo/yr
|
- |
$1,501
-
Tgal
|
- |
$2,284
-
Tgal
|
|
05 | 2.1117: Relocate oven / furnace to more efficient location | $11,196 | $2,080 |
$9,672
174,266
kWh
|
$1,524
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.1116: Improve combustion control capability | $4,114 | $3,000 | - | - |
$5,314
-
MMBtu
|
- | $(-1,200.0) | - | |
07 | 2.4151: Develop a repair/replace policy | $3,371 | $1,984 |
$2,960
53,327
kWh
|
$411
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $176,769 | $290,994 |
$150,551
2,712,607
kWh
|
$23,519
-
kW-mo/yr
|
$5,314
-
MMBtu
|
$1,501
-
Tgal
|
$(-6,400.0) |
$2,284
-
Tgal
|
||
TOTAL IMPLEMENTED | $11,402 | $9,124 |
$6,649
119,796
kWh
|
$968
-
kW-mo/yr
|
- |
$1,501
-
Tgal
|
- |
$2,284
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs