ITAC Assessment: UU0297
ITAC logo
ITAC Assessment: UU0297
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Roofing Membrane
NAICS 326299: All Other Rubber Product Manufacturing
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 110
Plant Area 240,000
ft2
Annual Production 307,000,000
units
Production Hrs. Annual 6,864
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $962,724 15,010,575
kWh
Electricity Demand $717,429 36,801
kW-mo/yr
Natural Gas $37,150 6,298
MMBtu
Waste Disposal Costs
Water Usage $36,600 6,960
Tgal
TOTAL YEARLY COSTS $1,753,903
RECOMMENDED SAVINGS* $52,377 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Personnel Changes Savings
01 2.2222: Convert liquid heaters from underfiring to immersion or submersion heating $6,550 $23,886 - - $6,550
-
MMBtu
- -
02 2.7442: Keep doors and windows shut when not on use $5,030 $43,200 - - $5,030
-
MMBtu
- -
03 3.4151: Minimize water usage $26,601 $91,000 - - - $1,311
-
Tgal
$25,290
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,000 $30,500 $2,100
33,000
kWh
$1,900
-
kW-mo/yr
- - -
05 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $7,190 $7,200 $5,160
80,700
kWh
$2,030
-
kW-mo/yr
- - -
06 2.4221: Install compressor air intakes in coolest locations $1,370 $6,700 $900
14,300
kWh
$470
-
kW-mo/yr
- - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $1,636 $530 $1,090
17,300
kWh
$546
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $52,377 $203,016 $9,250
145,300
kWh
$4,946
-
kW-mo/yr
$11,580
-
MMBtu
$1,311
-
Tgal
$25,290
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs