Assessment Year | 2022 |
---|---|
Principal Product | Concrete and Gypsum |
NAICS | 327390: Other Concrete Product Manufacturing |
SIC | 3272: Concrete Products, Except Block and Brick |
Sales Range | $10 M to 50M |
# of Employees | 65 |
Plant Area |
36,000
ft2
|
Annual Production | 132,000
units
|
Production Hrs. Annual | 3,120
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $10,963 | 305,600 |
kWh
|
$0.036 | |
Electricity Demand | $28,396 | 1,750 |
kW-mo/yr
|
$16.23 | |
Electricity Fees | $4,566 | - |
|
- | |
Natural Gas | $22,207 | 3,192 |
MMBtu
|
$6.96 | |
Fuel Oil #1 | $25,106 | 1,165 |
MMBtu
|
$21.55 | |
Fuel Oil #2 | $4,780 | 243 |
MMBtu
|
$19.65 | |
Waste Disposal Costs | |||||
Water Usage | $3,722 | 793 |
Tgal
|
$4.69 | |
Solid Waste (non-haz) | $92,026 | 2,688,120 |
lb
|
$0.034 | |
TOTAL YEARLY COSTS | $191,765 | ||||
RECOMMENDED SAVINGS* | $37,552 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $14,545 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #1 Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.9112: Use solar heat to heat water | $15,757 | $75,487 | - | - | - |
$15,757
-
MMBtu
|
- | |
02 | 3.1191: Change procedures / equipment / operating conditions | $7,250 | $5,000 | - | - | - | - | $7,250 | |
03 | 3.1191: Change procedures / equipment / operating conditions | $6,884 | $750 | - | - | - | - | $6,884 | |
04 | 2.3212: Optimize plant power factor | $4,008 | $3,433 | - |
$4,008
-
kW-mo/yr
|
- | - | - | |
05 | 2.2437: Recover waste heat from equipment | $1,912 | $1,585 | - | - |
$1,912
-
MMBtu
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $850 | $1,000 |
$295
8,206
kWh
|
$555
-
kW-mo/yr
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $626 | $1,700 |
$626
17,308
kWh
|
- | - | - | - | |
08 | 2.7263: Lower compressor pressure through a/c system modification | $265 | $750 |
$91
2,533
kWh
|
$174
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $37,552 | $89,705 |
$1,013
28,047
kWh
|
$4,736
-
kW-mo/yr
|
$1,912
-
MMBtu
|
$15,757
-
MMBtu
|
$14,134 | ||
TOTAL IMPLEMENTED | $14,545 | $9,218 |
$1,013
28,047
kWh
|
$4,736
-
kW-mo/yr
|
$1,912
-
MMBtu
|
- | $6,884 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #1 Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs