Assessment Year | 2022 |
---|---|
Principal Product | Sporting Goods |
NAICS | 339920: Sporting and Athletic Goods Manufacturing |
SIC | 3949: Sporting and Athletic Goods, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 350 |
Plant Area |
660,000
ft2
|
Annual Production | 660,000
thousand feet
|
Production Hrs. Annual | 8,112
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $206,375 | 5,349,600 |
kWh
|
$0.039 | |
Electricity Demand | $161,273 | 9,874 |
kW-mo/yr
|
$16.33 | |
Electricity Fees | $47,441 | - |
|
- | |
Natural Gas | $38,797 | 5,014 |
MMBtu
|
$7.74 | |
Waste Disposal Costs | |||||
Water Usage | $4,431 | 2,401 |
Tgal
|
$1.85 | |
TOTAL YEARLY COSTS | $458,317 | ||||
RECOMMENDED SAVINGS* | $35,636 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $1,293 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $10,629 | $10,629 |
$8,366
216,839
kWh
|
$2,263
-
kW-mo/yr
|
- | - | |
02 | 2.3137: Use power during off-peak periods | $10,548 | $18,900 | - |
$10,548
-
kW-mo/yr
|
- | - | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $8,310 | $28,263 |
$(-2,226.0)
(-57,712)
kWh
|
$(-1,461.3)
-
kW-mo/yr
|
$11,997
-
MMBtu
|
- | |
04 | 2.8113: Purchase gas directly from a contract gas supplier | $3,404 | $9,200 | - | - | - | $3,404 | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,293 | $198 |
$615
15,940
kWh
|
$678
-
kW-mo/yr
|
- | - | |
06 | 2.6231: Utilize controls to operate equipment only when needed | $1,070 | $150 |
$1,070
27,811
kWh
|
- | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $382 | $720 |
$100
2,590
kWh
|
$282
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $35,636 | $68,060 |
$7,925
205,468
kWh
|
$12,310
-
kW-mo/yr
|
$11,997
-
MMBtu
|
$3,404 | ||
TOTAL IMPLEMENTED | $1,293 | $198 |
$615
15,940
kWh
|
$678
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs