| Assessment Year | 2006 |
|---|---|
| Principal Product | paper products |
| NAICS | 322230: Stationery Product Manufacturing |
| SIC | 2675: Die-Cut Paper and Paperboard and Cardboard |
| Sales Range | $100 M to 500M |
| # of Employees | 265 |
| Plant Area |
312,400
ft2
|
| Annual Production | 102,000,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $103,883 | 4,035,840 |
kWh
|
$0.026 |
| Electricity Demand | $105,614 | 13,774 |
kW-mo/yr
|
$7.67 |
| Natural Gas | $24,990 | 2,709 |
MMBtu
|
$9.22 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $56,880 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3191: Use demand controller or load shedder | $22,930 | $20,000 | - |
$22,930
-
kW-mo/yr
|
- | |
| 02 | 2.4225: Install common header on compressors | $1,760 | $8,000 |
$1,760
62,740
kWh
|
- | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $17,680 | $1,560 |
$5,690
202,390
kWh
|
$11,990
-
kW-mo/yr
|
- | |
| 04 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $1,320 | $605 |
$1,230
43,640
kWh
|
$90
-
kW-mo/yr
|
- | |
| 05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $9,860 | $33,500 |
$1,300
46,245
kWh
|
$850
-
kW-mo/yr
|
$7,710
-
MMBtu
|
|
| 06 | 2.7231: Use radiant heater for spot heating | $3,330 | $17,000 | - | - |
$3,330
-
MMBtu
|
|
| TOTAL RECOMMENDED | $56,880 | $80,665 |
$9,980
355,015
kWh
|
$35,860
-
kW-mo/yr
|
$11,040
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs