Assessment Year | 2004 |
---|---|
Principal Product | joists |
NAICS | 332312: Fabricated Structural Metal Manufacturing |
SIC | 3441: Fabricated Structural Metal |
Sales Range | $50 M to 100M |
# of Employees | 295 |
Plant Area |
693,013
ft2
|
Annual Production | 150,000
ton
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $220,280 | 10,352,000 |
kWh
|
$0.021 |
Electricity Demand | $213,493 | 35,464 |
kW-mo/yr
|
$6.02 |
Electricity Fees | $17,147 | - |
|
- |
Natural Gas | $196,791 | 88,502 |
MMBtu
|
$2.22 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $110,757 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,337 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4322: Use or replace with energy efficient substitutes | $54,124 | $150,000 | - | - | - |
$54,124
-
MMBtu
|
- | |
02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $21,233 | $78,000 |
$(-266.0)
(-12,071)
kWh
|
$(-131.0)
-
kW-mo/yr
|
- |
$21,630
-
MMBtu
|
- | |
03 | 2.2437: Recover waste heat from equipment | $6,081 | $5,369 | - | - | - |
$6,081
-
MMBtu
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,398 | $308 |
$768
34,924
kWh
|
$630
-
kW-mo/yr
|
- | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,714 | $1,010 |
$2,048
93,101
kWh
|
$1,676
-
kW-mo/yr
|
- | - | $(-1,010.0) | |
06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $14,353 | - | - |
$14,353
-
kW-mo/yr
|
- | - | - | |
07 | 2.8112: Combine utility meters | $10,270 | - | - | - | $10,270 | - | - | |
08 | 2.6212: Turn off equipment during breaks, reduce operating time | $584 | - |
$584
26,520
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $110,757 | $234,687 |
$3,134
142,474
kWh
|
$16,528
-
kW-mo/yr
|
$10,270 |
$81,835
-
MMBtu
|
$(-1,010.0) | ||
TOTAL IMPLEMENTED | $27,337 | $1,010 |
$2,048
93,101
kWh
|
$16,029
-
kW-mo/yr
|
$10,270 | - | $(-1,010.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs