ITAC Assessment: UU0058
ITAC logo
ITAC Assessment: UU0058
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product joists
NAICS 332312: Fabricated Structural Metal Manufacturing
SIC 3441: Fabricated Structural Metal
Sales Range $50
M
to 100
M
# of Employees 295
Plant Area 693,013
ft2
Annual Production 150,000
ton
Production Hrs. Annual 4,160
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $220,280 10,352,000
kWh
Electricity Demand $213,493 35,464
kW-mo/yr
Electricity Fees $17,147 -
Natural Gas $196,791 88,502
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $110,757 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $27,337

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
01 2.4322: Use or replace with energy efficient substitutes $54,124 $150,000 - - - $54,124
-
MMBtu
-
02 2.7447: Install vinyl strip / high speed / air curtain doors $21,233 $78,000 $(-266.0)
(-12,071)
kWh
$(-131.0)
-
kW-mo/yr
- $21,630
-
MMBtu
-
03 2.2437: Recover waste heat from equipment $6,081 $5,369 - - - $6,081
-
MMBtu
-
04 2.4221: Install compressor air intakes in coolest locations $1,398 $308 $768
34,924
kWh
$630
-
kW-mo/yr
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,714 $1,010 $2,048
93,101
kWh
$1,676
-
kW-mo/yr
- - $(-1,010.0)
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $14,353 - - $14,353
-
kW-mo/yr
- - -
07 2.8112: Combine utility meters $10,270 - - - $10,270 - -
08 2.6212: Turn off equipment during breaks, reduce operating time $584 - $584
26,520
kWh
- - - -
TOTAL RECOMMENDED $110,757 $234,687 $3,134
142,474
kWh
$16,528
-
kW-mo/yr
$10,270 $81,835
-
MMBtu
$(-1,010.0)
TOTAL IMPLEMENTED $27,337 $1,010 $2,048
93,101
kWh
$16,029
-
kW-mo/yr
$10,270 - $(-1,010.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs