ITAC Assessment: UM0468
ITAC logo
ITAC Assessment: UM0468
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Anodize, Hardcoat, conversion coatings on aluminum
NAICS 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $10
M
to 50
M
# of Employees 148
Plant Area 55,750
ft2
Annual Production 100,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $576,647 7,987,560
kWh
Natural Gas $32,206 31,475
MMBtu
TOTAL YEARLY COSTS $608,853
RECOMMENDED SAVINGS* $28,291 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,797

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.4221: Install compressor air intakes in coolest locations $695 $1,500 $695
9,651
kWh
- -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,680 $2,150 $4,680
64,995
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $15,125 $43,167 $13,209
183,456
kWh
- $1,916
04 2.2511: Insulate bare equipment $3,084 $2,000 $3,084
42,833
kWh
- -
05 2.2511: Insulate bare equipment $1,588 $1,500 $1,588
22,050
kWh
- -
06 2.6231: Utilize controls to operate equipment only when needed $3,119 $10,000 - $3,119
-
MMBtu
-
TOTAL RECOMMENDED $28,291 $60,317 $23,256
322,985
kWh
$3,119
-
MMBtu
$1,916
TOTAL IMPLEMENTED $19,797 $46,667 $17,881
248,339
kWh
- $1,916
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs