| Assessment Year | 1985 |
|---|---|
| Principal Product | MOLDED RUBBER PRODUCTS |
| NAICS |
n/a
|
| SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 310 |
| Plant Area |
n/a
|
| Annual Production | 6,600
ton
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $509,491 | 10,334,994 |
kWh
|
$0.049 |
| Natural Gas | $371,474 | 84,386 |
MMBtu
|
$4.40 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $90,740 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $77,418 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2127: Flash condensate to produce lower pressure steam | $76,200 | $15,600 | - |
$76,200
-
MMBtu
|
|
| 02 | 2.2136: Install / repair insulation on steam lines | $12,690 | $1,135 | - |
$12,690
-
MMBtu
|
|
| 03 | 2.2135: Repair and eliminate steam leaks | $1,218 | $45 | - |
$1,218
-
MMBtu
|
|
| 04 | 2.7261: Install timers and/or thermostats | $632 | $450 |
$372
12,896
kWh
|
$260
-
MMBtu
|
|
| TOTAL RECOMMENDED | $90,740 | $17,230 |
$372
12,896
kWh
|
$90,368
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $77,418 | $15,645 | - |
$77,418
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs