ITAC Assessment: IC0257
ITAC logo
ITAC Assessment: IC0257
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Sporting Goods
NAICS 451110: Sporting Goods Stores
SIC 5941: Sporting Goods Stores and Bicycle Shops
Sales Range $50
M
to 100
M
# of Employees 50
Plant Area 110,000
ft2
Annual Production 9,500
units
Production Hrs. Annual 4,380
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $207,884 2,499,686
kWh
Natural Gas $11,191 1,937
MMBtu
Waste Disposal Costs
Water Usage $20,912 687
Tgal
TOTAL YEARLY COSTS $239,987
RECOMMENDED SAVINGS* $6,100 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,841

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,970 $13,094 $3,970
47,835
kWh
-
02 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $339 - $339
4,080
kWh
-
03 2.7134: Use photocell controls $259 $355 $259
3,115
kWh
-
04 2.7492: Use proper thickness of insulation on building envelope $1,532 $6,144 - $1,532
-
MMBtu
TOTAL RECOMMENDED $6,100 $19,593 $4,568
55,030
kWh
$1,532
-
MMBtu
TOTAL IMPLEMENTED $5,841 $19,238 $4,309
51,915
kWh
$1,532
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs