Assessment Year | 2020 |
---|---|
Principal Product | Finished Textiles and Other Flocked Products |
NAICS | 313320: Fabric Coating Mills |
SIC | 2269: Finishers of Textiles, Not elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 35 |
Plant Area |
180,000
ft2
|
Annual Production | 12,000
thousand feet
|
Production Hrs. Annual | 2,700
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $117,281 | 981,000 |
kWh
|
$0.12 | |
Electricity Demand | $34,440 | 5,322 |
kW-mo/yr
|
$6.47 | |
Electricity Fees | $2,676 | - |
|
- | |
Natural Gas | $88,784 | 10,150 |
MMBtu
|
$8.75 | |
Waste Disposal Costs | |||||
Water Usage | $2,136 | 412 |
Tgal
|
$5.19 | |
Water Disposal | $2,349 | 412 |
Tgal
|
$5.70 | |
TOTAL YEARLY COSTS | $247,666 | ||||
RECOMMENDED SAVINGS* | $59,402 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2212: Use minimum safe oven ventilation | $48,924 | $61,470 |
$9,930
82,749
kWh
|
- |
$38,994
-
MMBtu
|
|
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,991 | $23,275 |
$8,991
74,928
kWh
|
- | - | |
03 | 2.3212: Optimize plant power factor | $997 | $1,400 | - |
$997
-
kW-mo/yr
|
- | |
04 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $490 | $1,785 | - | - |
$490
-
MMBtu
|
|
TOTAL RECOMMENDED | $59,402 | $87,930 |
$18,921
157,677
kWh
|
$997
-
kW-mo/yr
|
$39,484
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs