ITAC Assessment: UM0464
ITAC logo
ITAC Assessment: UM0464
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Wood Moldings and Railings
NAICS 321918: Other Millwork (including Flooring)
SIC 2431: Millwork
Sales Range $5
M
to 10
M
# of Employees 80
Plant Area 168,500
ft2
Annual Production 800,000
units
Production Hrs. Annual 2,080
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $194,264 2,595,239
kWh
Natural Gas $45,530 11,298
MMBtu
TOTAL YEARLY COSTS $239,794
RECOMMENDED SAVINGS* $9,832 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,629

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4221: Install compressor air intakes in coolest locations $361 $2,000 $361
4,823
kWh
-
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,842 $5,500 $1,842
24,627
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $4,786 $3,794 $4,786
63,986
kWh
-
04 2.7243: Improve air circulation with destratification fans / other methods $736 $150 $(-43.5)
(-582)
kWh
$780
-
MMBtu
05 2.7444: Close holes and openings in building such as broken windows $2,107 $7,900 - $2,107
-
MMBtu
TOTAL RECOMMENDED $9,832 $19,344 $6,945
92,854
kWh
$2,887
-
MMBtu
TOTAL IMPLEMENTED $7,629 $11,844 $4,742
63,404
kWh
$2,887
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs