| Assessment Year | 2015 |
|---|---|
| Principal Product | Automotive interior components |
| NAICS | 332111: Iron and Steel Forging |
| SIC | 3465: Automotive Stampings |
| Sales Range | $50 M to 100M |
| # of Employees | 239 |
| Plant Area |
150,000
ft2
|
| Annual Production | 1,000,000
pieces
|
| Production Hrs. Annual | 7,500
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $550,000 | 7,560,000 |
kWh
|
$0.073 |
| Natural Gas | $160,000 | 18,450 |
MMBtu
|
$8.67 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $48,620 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $19,125 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4239: Eliminate or reduce compressed air usage | $19,380 | $5,000 |
$19,380
266,400
kWh
|
- | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,831 | $1,000 |
$7,831
107,280
kWh
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $3,442 | $1,500 |
$3,442
47,312
kWh
|
- | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $10,115 | $5,400 | - |
$10,115
-
MMBtu
|
|
| 05 | 2.2437: Recover waste heat from equipment | $7,852 | $4,000 | - |
$7,852
-
MMBtu
|
|
| TOTAL RECOMMENDED | $48,620 | $16,900 |
$30,653
420,992
kWh
|
$17,967
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $19,125 | $6,500 |
$11,273
154,592
kWh
|
$7,852
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs