Assessment Year | 2010 |
---|---|
Principal Product | Drawn Steel |
NAICS | 331222: Steel Wire Drawing |
SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
Sales Range | $50 M to 100M |
# of Employees | 60 |
Plant Area |
180,000
ft2
|
Annual Production | 60,000
ton
|
Production Hrs. Annual | 3,570
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $295,508 | 6,387,080 |
kWh
|
$0.046 |
Electricity Demand | $352,421 | 22,402 |
kW-mo/yr
|
$15.73 |
Natural Gas | $160,364 | 16,256 |
MMBtu
|
$9.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $93,631 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $92,812 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $22,536 | $77,254 |
$11,378
245,902
kWh
|
$11,158
-
kW-mo/yr
|
- | |
02 | 2.4323: Use optimum size and capacity equipment | $15,991 | $107,000 |
$15,991
345,600
kWh
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $4,966 | $13,000 |
$3,031
65,497
kWh
|
$1,935
-
kW-mo/yr
|
- | |
04 | 2.7135: Install occupancy sensors | $1,051 | - |
$1,051
22,708
kWh
|
- | - | |
05 | 2.2437: Recover waste heat from equipment | $43,773 | $13,000 | - | - |
$43,773
-
MMBtu
|
|
06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,455 | $3,500 | - | - |
$3,455
-
MMBtu
|
|
07 | 2.2515: Use optimum thickness insulation | $1,040 | $22,500 | - | - |
$1,040
-
MMBtu
|
|
08 | 2.7494: Install storm windows and doors | $819 | - | - | - |
$819
-
MMBtu
|
|
TOTAL RECOMMENDED | $93,631 | $236,254 |
$31,451
679,707
kWh
|
$13,093
-
kW-mo/yr
|
$49,087
-
MMBtu
|
||
TOTAL IMPLEMENTED | $92,812 | $236,254 |
$31,451
679,707
kWh
|
$13,093
-
kW-mo/yr
|
$48,268
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs