Assessment Year | 2005 |
---|---|
Principal Product | Cardboard Boxes, Plastic Returnable Packaging |
NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $5 M to 10M |
# of Employees | 46 |
Plant Area |
130,000
ft2
|
Annual Production | 92,000,000
thousand feet
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $54,486 | 1,494,804 |
kWh
|
$0.036 |
Electricity Demand | $51,040 | 5,326 |
kW-mo/yr
|
$9.58 |
Electricity Fees | $2,396 | - |
|
- |
Natural Gas | $66,636 | 8,885 |
MMBtu
|
$7.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $26,735 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,550 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7231: Use radiant heater for spot heating | $7,943 | $12,500 | - | - |
$7,943
-
MMBtu
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,268 | $11,077 |
$4,060
110,393
kWh
|
$3,208
-
kW-mo/yr
|
- | |
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $4,868 | $2,650 | - | - |
$4,868
-
MMBtu
|
|
04 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $2,753 | $6,230 | - | - |
$2,753
-
MMBtu
|
|
05 | 2.3132: Recharge batteries on during off-peak demand periods | $2,242 | - | - |
$2,242
-
kW-mo/yr
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $1,296 | $1,950 |
$578
15,849
kWh
|
$718
-
kW-mo/yr
|
- | |
07 | 2.7444: Close holes and openings in building such as broken windows | $365 | $720 | - | - |
$365
-
MMBtu
|
|
TOTAL RECOMMENDED | $26,735 | $35,127 |
$4,638
126,242
kWh
|
$6,168
-
kW-mo/yr
|
$15,929
-
MMBtu
|
||
TOTAL IMPLEMENTED | $16,550 | $22,627 |
$4,638
126,242
kWh
|
$3,926
-
kW-mo/yr
|
$7,986
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs