Assessment Year | 2005 |
---|---|
Principal Product | Interior Door Panels,Interior Dashboards,Interior Flooring |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $100 M to 500M |
# of Employees | 683 |
Plant Area |
348,000
ft2
|
Annual Production | 3,936,831
pieces
|
Production Hrs. Annual | 5,760
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,299,669 | 23,587,000 |
kWh
|
$0.055 |
Electricity Demand | $643,405 | 44,880 |
kW-mo/yr
|
$14.34 |
Electricity Fees | $1,954 | - |
|
- |
Natural Gas | $229,809 | 26,436 |
MMBtu
|
$8.69 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $282,015 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $66,642 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $208,751 | $887,900 |
$348,810
6,342,000
kWh
|
$181,889
-
kW-mo/yr
|
$(-321,948.0)
-
MMBtu
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $22,506 | $675 |
$14,793
268,954
kWh
|
$7,713
-
kW-mo/yr
|
- | |
03 | 2.2437: Recover waste heat from equipment | $17,467 | $1,200 | - | - |
$17,467
-
MMBtu
|
|
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $9,493 | $8,770 | - | - |
$9,493
-
MMBtu
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,726 | $13,103 |
$3,484
63,244
kWh
|
$3,242
-
kW-mo/yr
|
- | |
06 | 2.2511: Insulate bare equipment | $6,622 | $206 |
$3,008
54,600
kWh
|
$3,614
-
kW-mo/yr
|
- | |
07 | 2.4221: Install compressor air intakes in coolest locations | $6,116 | $1,000 |
$4,022
73,093
kWh
|
$2,094
-
kW-mo/yr
|
- | |
08 | 2.2531: Re-size charging openings or add movable cover or door | $4,334 | $1,250 | - | - |
$4,334
-
MMBtu
|
|
TOTAL RECOMMENDED | $282,015 | $914,104 |
$374,117
6,801,891
kWh
|
$198,552
-
kW-mo/yr
|
$(-290,654.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $66,642 | $25,998 |
$22,299
405,291
kWh
|
$13,049
-
kW-mo/yr
|
$31,294
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs