ITAC Assessment: UM0286
ITAC logo
ITAC Assessment: UM0286
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Automotive Testing Equipment
NAICS 336350: Motor Vehicle Transmission and Power Train Parts Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $10
M
to 50
M
# of Employees 157
Plant Area 130,000
ft2
Annual Production 80
pieces
Production Hrs. Annual 4,680
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $73,304 2,043,805
kWh
Electricity Demand $56,579 5,804
kW-mo/yr
Electricity Fees $2,935 -
Natural Gas $29,280 3,860
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $27,288 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,859

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7491: Insulate glazing, walls, ceilings, and roofs $9,539 $27,000 $922
14,177
kWh
- $8,617
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $6,301 $13,476 $3,588
100,038
kWh
$2,713
-
kW-mo/yr
-
03 2.7447: Install vinyl strip / high speed / air curtain doors $3,775 $1,900 $283
4,349
kWh
- $3,492
-
MMBtu
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,376 $450 $2,079
57,908
kWh
$1,297
-
kW-mo/yr
-
05 2.2437: Recover waste heat from equipment $1,619 $500 - - $1,619
-
MMBtu
06 2.7124: Make a practice of turning off lights when not needed $1,608 $75 $969
26,997
kWh
$639
-
kW-mo/yr
-
07 2.7135: Install occupancy sensors $618 $736 $618
17,203
kWh
- -
08 2.4221: Install compressor air intakes in coolest locations $352 $1,000 $215
5,978
kWh
$137
-
kW-mo/yr
-
09 2.7444: Close holes and openings in building such as broken windows $100 $45 $11
176
kWh
- $89
-
MMBtu
TOTAL RECOMMENDED $27,288 $45,182 $8,685
226,826
kWh
$4,786
-
kW-mo/yr
$13,817
-
MMBtu
TOTAL IMPLEMENTED $8,859 $2,470 $3,342
89,430
kWh
$1,936
-
kW-mo/yr
$3,581
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs