| Assessment Year | 2026 |
|---|---|
| Principal Product | Pneumatically-driven nails |
| NAICS | 332618: Other Fabricated Wire Product Manufacturing |
| SIC | 3315: Steel Wiredrawing and Steel Nails and Spikes |
| Sales Range | $10 M to 50M |
| # of Employees | 40 |
| Plant Area |
125,000
ft2
|
| Annual Production | 2,650
ton
|
| Production Hrs. Annual | 1,920
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $212,335 | 3,515,400 |
kWh
|
$0.060 | |
| Electricity Demand | $129,010 | 14,632 |
kW-mo/yr
|
$8.82 | |
| Natural Gas | $72,546 | 9,022 |
MMBtu
|
$8.04 | |
| Waste Disposal Costs | |||||
| Water Usage | $19,600 | 4,155 |
Tgal
|
$4.72 | |
| Water Disposal | $8,546 | 3,408 |
Tgal
|
$2.51 | |
| TOTAL YEARLY COSTS | $442,037 | ||||
| RECOMMENDED SAVINGS* | $39,349 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7211: Clean and maintain refrigerant condensers and towers | $294 | $935 |
$294
4,900
kWh
|
- | |
| 02 | 2.7226: Use computer programs to optimize hvac performance | $2,462 | $8,120 |
$2,462
41,038
kWh
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,988 | $13,005 |
$9,988
166,464
kWh
|
- | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $25,293 | $40,074 |
$25,293
421,551
kWh
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,312 | $7,084 |
$739
12,306
kWh
|
$573
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $39,349 | $69,218 |
$38,776
646,259
kWh
|
$573
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs