ITAC Assessment: UM0231
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Bottled Water
NAICS 312112: Bottled Water Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $100
M
to 500
M
# of Employees 150
Plant Area 105,000
ft2
Annual Production 0
units
Production Hrs. Annual 6,188
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $272,933 5,383,512
kWh
Electricity Demand $35,526 33,906
kW-mo/yr
Electricity Fees $40,140 -
Natural Gas $73,339 16,489
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,899 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,750 $7,445 $2,844
56,095
kWh
$1,906
-
kW-mo/yr
-
02 2.4221: Install compressor air intakes in coolest locations $4,000 $2,250 $2,517
49,253
kWh
$1,483
-
kW-mo/yr
-
03 2.6231: Utilize controls to operate equipment only when needed $1,320 $1,500 $1,320
26,000
kWh
- -
04 2.2447: Heat water with exhaust heat $6,519 $7,500 - - $6,519
-
MMBtu
05 2.1224: Replace boiler $6,310 $2,500 - - $6,310
-
MMBtu
TOTAL RECOMMENDED $22,899 $21,195 $6,681
131,348
kWh
$3,389
-
kW-mo/yr
$12,829
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs