Assessment Year | 2003 |
---|---|
Principal Product | Bottled Water |
NAICS | 312112: Bottled Water Manufacturing |
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $100 M to 500M |
# of Employees | 150 |
Plant Area |
105,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,188
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $272,933 | 5,383,512 |
kWh
|
$0.051 |
Electricity Demand | $35,526 | 33,906 |
kW-mo/yr
|
$1.05 |
Electricity Fees | $40,140 | - |
|
- |
Natural Gas | $73,339 | 16,489 |
MMBtu
|
$4.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,899 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,750 | $7,445 |
$2,844
56,095
kWh
|
$1,906
-
kW-mo/yr
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $4,000 | $2,250 |
$2,517
49,253
kWh
|
$1,483
-
kW-mo/yr
|
- | |
03 | 2.6231: Utilize controls to operate equipment only when needed | $1,320 | $1,500 |
$1,320
26,000
kWh
|
- | - | |
04 | 2.2447: Heat water with exhaust heat | $6,519 | $7,500 | - | - |
$6,519
-
MMBtu
|
|
05 | 2.1224: Replace boiler | $6,310 | $2,500 | - | - |
$6,310
-
MMBtu
|
|
TOTAL RECOMMENDED | $22,899 | $21,195 |
$6,681
131,348
kWh
|
$3,389
-
kW-mo/yr
|
$12,829
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs