| Assessment Year | 1999 |
|---|---|
| Principal Product | Aerial Boom Devices |
| NAICS |
n/a
|
| SIC | 3535: Conveyors and Conveying Equipment |
| Sales Range | $1 M to 5M |
| # of Employees | 63 |
| Plant Area |
56,000
ft2
|
| Annual Production | 2,000
pieces
|
| Production Hrs. Annual | 4,050
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $46,459 | 1,600,234 |
kWh
|
$0.029 |
| Electricity Demand | $27,479 | 8,086 |
kW-mo/yr
|
$3.40 |
| Natural Gas | $35,419 | 7,610 |
MMBtu
|
$4.65 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $82,242 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $63,404 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $157 | $65 |
$95
3,224
kWh
|
$62
-
kW-mo/yr
|
- | - | |
| 02 | 2.7261: Install timers and/or thermostats | $503 | $400 |
$503
30,774
kWh
|
- | - | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $183 | $20 |
$108
3,224
kWh
|
$75
-
kW-mo/yr
|
- | - | |
| 04 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $40,406 | $8,165 | - | - | $40,406 | - | |
| 05 | 4.431: Train operators for maximum operating efficiency | $18,655 | $1,448 | - | - | $18,655 | - | |
| 06 | 4.423: Move product using mechanical means | $22,338 | $5,000 | - | - | - | $22,338 | |
| TOTAL RECOMMENDED | $82,242 | $15,098 |
$706
37,222
kWh
|
$137
-
kW-mo/yr
|
$59,061 | $22,338 | ||
| TOTAL IMPLEMENTED | $63,404 | $13,630 |
$598
33,998
kWh
|
$62
-
kW-mo/yr
|
$40,406 | $22,338 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings | By-product Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs