ITAC Assessment: UL0195
ITAC logo
ITAC Assessment: UL0195
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product isolated soy protein
NAICS
n/a
SIC 2075: Soybean Oil Mills
Sales Range $10
M
to 50
M
# of Employees 96
Plant Area 113,000
ft2
Annual Production 45,000,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $667,544 26,655,335
kWh
Electricity Demand $351,329 100,224
kW-mo/yr
Natural Gas $1,795,015 457,045
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,890,868 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $177,628

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Water Consumption Savings Primary Product Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $7,850 $20 $6,541
261,137
kWh
$1,309
-
kW-mo/yr
- - - - - -
02 2.4221: Install compressor air intakes in coolest locations $4,732 $260 $3,942
157,386
kWh
$790
-
kW-mo/yr
- - - - - -
03 2.7261: Install timers and/or thermostats $6,368 $800 - - $6,368
-
MMBtu
- - - - -
04 3.5248: Separate and recycle scrap metal to foundry or for sale $2,628 - - - - - $2,628
-
lb
- - -
05 3.3128: Utilize other methods to remove contaminants $6,458,418 $3,180,000 - - $1,094,959
-
MMBtu
$5,363,459
-
Tgal
- - - -
06 3.4151: Minimize water usage $235,872 $666,500 - - - $151,956
-
Tgal
- - $83,916
-
Tgal
-
07 4.624: Hire additional personnel to reduce changeout time $70,000 - - - - - - $70,000 - -
08 4.512: Condense operation into one building $105,000 $300,000 - - - - - - - $105,000
TOTAL RECOMMENDED $6,890,868 $4,147,580 $10,483
418,523
kWh
$2,099
-
kW-mo/yr
$1,101,327
-
MMBtu
$5,515,415
-
Tgal
$2,628
-
lb
$70,000 $83,916
-
Tgal
$105,000
TOTAL IMPLEMENTED $177,628 $300,000 - - - - $2,628
-
lb
$70,000 - $105,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Water Consumption Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs