ITAC Assessment: UL0184
ITAC logo
ITAC Assessment: UL0184
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Aluminum Die Castings
NAICS
n/a
SIC 3363: Aluminum Die-Castings
Sales Range $50
M
to 100
M
# of Employees 400
Plant Area 225,000
ft2
Annual Production 50,000,000
lb
Production Hrs. Annual 6,500
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $516,365 19,597,011
kWh
Electricity Demand $346,419 33,996
kW-mo/yr
Electricity Fees $142,933 -
Natural Gas $633,750 180,257
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $570,639 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $350,698

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Primary Product Savings
01 2.2414: Use waste heat from hot flue gases to preheat $31,231 $59,862 - - $31,231
-
MMBtu
- - - - -
02 2.2424: Use heat in flue gases to preheat products or materials $9,676 $22,454 - - $9,676
-
MMBtu
- - - - -
03 4.131: Modify process to reduce material use/cost $5,672 $90,000 - - $1,922
-
MMBtu
- - - $3,750 -
04 2.2515: Use optimum thickness insulation $25,680 $14,000 $25,680
500,586
kWh
- - - - - - -
05 2.3212: Optimize plant power factor $6,000 $9,270 - $6,000 - - - - - -
06 2.1122: Re-size charging openings or add a movable door on equipment $10,630 $20,000 - - $10,630
-
MMBtu
- - - - -
07 2.6218: Turn off equipment when not in use $4,146 - $4,146
80,891
kWh
- - - - - - -
08 2.4221: Install compressor air intakes in coolest locations $3,090 $1,200 $3,090
60,082
kWh
- - - - - - -
09 2.6241: Reduce temperature of process equipment when on standby $4,400 - - - $4,400
-
MMBtu
- - - - -
10 3.3132: Use reverse osmosis to concentrate material $21,700 $18,000 - - - $22,200
-
Tgal
- $(-500.0) - -
11 4.446: Automate finishing process $315,748 $222,000 - - - - $315,748 - - -
12 4.625: Develop standard operating procedures $110,952 $61,340 - - - - $110,952 - - -
13 4.611: Begin a practice of predictive / preventative maintenance $21,714 $4,200 $11,940
232,708
kWh
- - - - $2,094 - $7,680
TOTAL RECOMMENDED $570,639 $522,326 $44,856
874,267
kWh
$6,000 $57,859
-
MMBtu
$22,200
-
Tgal
$426,700 $1,594 $3,750 $7,680
TOTAL IMPLEMENTED $350,698 $236,670 $19,176
373,681
kWh
$6,000 - - $315,748 $2,094 - $7,680
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs