| Assessment Year | 2024 |
|---|---|
| Principal Product | Landing Gears |
| NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 220 |
| Plant Area |
100,000
ft2
|
| Annual Production | 1,200
pieces
|
| Production Hrs. Annual | 7,000
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $484,913 | 8,869,200 |
kWh
|
$0.055 | |
| Electricity Demand | $312,033 | 16,674 |
kW-mo/yr
|
$18.71 | |
| Electricity Fees | $134,214 | - |
|
- | |
| Natural Gas | $18,015 | 1,155 |
MMBtu
|
$15.60 | |
| Waste Disposal Costs | |||||
| Water Usage | $22,834 | 1,952 |
Tgal
|
$11.70 | |
| Water Disposal | $28,983 | 1,952 |
Tgal
|
$14.85 | |
| TOTAL YEARLY COSTS | $1,000,992 | ||||
| RECOMMENDED SAVINGS* | $508,032 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $292,161 | $663,964 |
$80,524
1,464,073
kWh
|
$211,637
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.8114: Change rate schedules or other changes in utility service | $116,907 | - | - | - | - | - | $116,907 | |
| 03 | 2.7221: Lower temperature during the winter season and vice-versa | $52,928 | $1,320 |
$38,107
692,862
kWh
|
$14,821
-
kW-mo/yr
|
- | - | - | |
| 04 | 3.4155: Meter waste water | $26,088 | $956 | - | - | - |
$26,088
-
Tgal
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,979 | $1,660 |
$3,771
68,568
kWh
|
$2,208
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4239: Eliminate or reduce compressed air usage | $9,248 | $860 |
$5,841
106,199
kWh
|
$3,407
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $2,582 | $1,027 |
$884
16,079
kWh
|
$842
-
kW-mo/yr
|
$856
-
MMBtu
|
- | - | |
| 08 | 2.2628: Utilize a less expensive cooling method | $2,139 | $40 |
$1,351
24,570
kWh
|
$788
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $508,032 | $669,827 |
$130,478
2,372,351
kWh
|
$233,703
-
kW-mo/yr
|
$856
-
MMBtu
|
$26,088
-
Tgal
|
$116,907 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs