Assessment Year | 2018 |
---|---|
Principal Product | Plastic Products |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 190 |
Plant Area |
80,000
ft2
|
Annual Production | 28,757,305
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $214,328 | 6,151,000 |
kWh
|
$0.035 | |
Electricity Demand | $292,108 | 17,235 |
kW-mo/yr
|
$16.95 | |
Electricity Fees | $2,736 | - |
|
- | |
Natural Gas | $5,859 | 795 |
MMBtu
|
$7.37 | |
Waste Disposal Costs | |||||
Water Usage | $6,336 | 1,508,600 |
Tgal
|
$0.004 | |
Water Disposal | $4,676 | 1,509 |
Tgal
|
$3.10 | |
TOTAL YEARLY COSTS | $526,043 | ||||
RECOMMENDED SAVINGS* | $53,657 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $1,020 | $1,734 |
$1,020
29,142
kWh
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,390 | $4,154 |
$1,440
41,244
kWh
|
$2,950
-
kW-mo/yr
|
- | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $1,644 | $147 |
$848
24,211
kWh
|
$796
-
kW-mo/yr
|
- | |
04 | 2.4152: Use only certified motor repair shops | $195 | $238 |
$195
5,572
kWh
|
- | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,550 | $2,320 |
$1,838
52,520
kWh
|
$1,712
-
kW-mo/yr
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $459 | $1,500 |
$459
13,125
kWh
|
- | - | |
07 | 2.4235: Remove or close off unneeded compressed air lines | $2,031 | - |
$2,031
58,032
kWh
|
- | - | |
08 | 2.4322: Use or replace with energy efficient substitutes | $6,253 | $9,350 |
$1,642
46,746
kWh
|
$4,611
-
kW-mo/yr
|
- | |
09 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $2,112 | $1,500 |
$2,112
60,333
kWh
|
- | - | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,686 | $1,200 |
$2,686
76,752
kWh
|
- | - | |
11 | 2.2511: Insulate bare equipment | $1,814 | $704 |
$1,061
30,318
kWh
|
$753
-
kW-mo/yr
|
- | |
12 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $493 | $1,150 |
$493
14,095
kWh
|
- | - | |
13 | 2.4323: Use optimum size and capacity equipment | $24,936 | $117,925 |
$12,800
365,737
kWh
|
$12,136
-
kW-mo/yr
|
- | |
14 | 3.4116: Meter recycled water (to reduce sewer charges) | $1,393 | $1,316 | - | - |
$1,393
-
Tgal
|
|
15 | 2.7224: Reduce space conditioning during non-working hours | $681 | - |
$681
19,469
kWh
|
- | - | |
TOTAL RECOMMENDED | $53,657 | $143,238 |
$29,306
837,296
kWh
|
$22,958
-
kW-mo/yr
|
$1,393
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs