| Assessment Year | 2007 |
|---|---|
| Principal Product | Medical Devices |
| NAICS | 325412: Pharmaceutical Preparation Manufacturing |
| SIC | 2834: Pharmaceutical Preparations |
| Sales Range | $50 M to 100M |
| # of Employees | 102 |
| Plant Area |
41,893
ft2
|
| Annual Production | 3,480,000
pieces
|
| Production Hrs. Annual | 2,184
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $64,343 | 811,085 |
kWh
|
$0.079 |
| Electricity Demand | $18,284 | 2,658 |
kW-mo/yr
|
$6.88 |
| LPG | $24,000 | 1,146 |
MMBtu
|
$20.94 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $29,480 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,818 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6232: Install set-back timers | $504 | $144 |
$504
5,139
kWh
|
- | |
| 02 | 2.7273: Install desiccant humidity control system | $5,429 | $12,800 |
$5,429
55,393
kWh
|
- | |
| 03 | 2.7243: Improve air circulation with destratification fans / other methods | $7,655 | $1,826 |
$7,655
78,111
kWh
|
- | |
| 04 | 2.5194: Redesign process | $10,558 | $8,150 |
$10,558
140,772
kWh
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,391 | $590 |
$1,391
14,191
kWh
|
- | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $189 | - |
$189
1,927
kWh
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,305 | $6,526 |
$973
12,975
kWh
|
$332
-
kW-mo/yr
|
|
| 08 | 2.7135: Install occupancy sensors | $1,504 | $894 |
$1,504
15,342
kWh
|
- | |
| 09 | 2.4221: Install compressor air intakes in coolest locations | $945 | $1,521 |
$656
8,736
kWh
|
$289
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $29,480 | $32,451 |
$28,859
332,586
kWh
|
$621
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $8,818 | $20,060 |
$8,486
89,625
kWh
|
$332
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs