ITAC Assessment: UF0397
ITAC logo
ITAC Assessment: UF0397
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Medical Devices
NAICS 325412: Pharmaceutical Preparation Manufacturing
SIC 2834: Pharmaceutical Preparations
Sales Range $50
M
to 100
M
# of Employees 102
Plant Area 41,893
ft2
Annual Production 3,480,000
pieces
Production Hrs. Annual 2,184
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $64,343 811,085
kWh
Electricity Demand $18,284 2,658
kW-mo/yr
LPG $24,000 1,146
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,480 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,818

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.6232: Install set-back timers $504 $144 $504
5,139
kWh
-
02 2.7273: Install desiccant humidity control system $5,429 $12,800 $5,429
55,393
kWh
-
03 2.7243: Improve air circulation with destratification fans / other methods $7,655 $1,826 $7,655
78,111
kWh
-
04 2.5194: Redesign process $10,558 $8,150 $10,558
140,772
kWh
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,391 $590 $1,391
14,191
kWh
-
06 2.4231: Reduce the pressure of compressed air to the minimum required $189 - $189
1,927
kWh
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,305 $6,526 $973
12,975
kWh
$332
-
kW-mo/yr
08 2.7135: Install occupancy sensors $1,504 $894 $1,504
15,342
kWh
-
09 2.4221: Install compressor air intakes in coolest locations $945 $1,521 $656
8,736
kWh
$289
-
kW-mo/yr
TOTAL RECOMMENDED $29,480 $32,451 $28,859
332,586
kWh
$621
-
kW-mo/yr
TOTAL IMPLEMENTED $8,818 $20,060 $8,486
89,625
kWh
$332
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs