ITAC Assessment: UK1511
ITAC logo
ITAC Assessment: UK1511
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Dairy Products and Fruit Juice
NAICS 311511: Fluid Milk Manufacturing
SIC 2026: Fluid Milk
Sales Range $100
M
to 500
M
# of Employees 183
Plant Area 125,876
ft2
Annual Production 449,857,161
ton
Production Hrs. Annual 8,760
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $582,465 15,321,000
kWh
Electricity Demand $354,643 32,839
kW-mo/yr
Electricity Fees $149,956 -
Natural Gas $250,638 54,961
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $562,289 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $502,566

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
01 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $457,639 $1,000,000 $496,236
13,939,200
kWh
$263,120
-
kW-mo/yr
- $(-301,717.0)
-
MMBtu
-
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $42,293 - - - $42,293 - -
03 2.3212: Optimize plant power factor $9,011 $8,260 - - $9,011 - -
04 2.8114: Change rate schedules or other changes in utility service $596 - - - $596 - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $24,582 $51,370 $14,699
412,894
kWh
$13,042
-
kW-mo/yr
- - $(-3,159.0)
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,159 $1,371 $322
9,044
kWh
$172
-
kW-mo/yr
- - $1,665
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,050 - $3,249
91,265
kWh
$801
-
kW-mo/yr
- - -
08 2.4221: Install compressor air intakes in coolest locations $737 $1,500 $737
20,690
kWh
- - - -
09 2.4321: Upgrade obsolete equipment $2,127 $14,000 $2,127
59,758
kWh
- - - -
10 2.4152: Use only certified motor repair shops $2,199 $1,865 $2,199
61,761
kWh
- - - -
11 2.4111: Utilize energy-efficient belts and other improved mechanisms $552 - $552
15,500
kWh
- - - -
12 2.2442: Preheat combustion air with waste heat $7,205 $18,400 - - - $7,205
-
MMBtu
-
13 2.1222: Install turbulators $8,026 $9,000 - - - $8,026
-
MMBtu
-
14 2.2123: Insulate feedwater tank $1,113 $862 - - - $1,113
-
MMBtu
-
TOTAL RECOMMENDED $562,289 $1,106,628 $520,121
14,610,112
kWh
$277,135
-
kW-mo/yr
$51,900 $(-285,373.0)
-
MMBtu
$(-1,494.0)
TOTAL IMPLEMENTED $502,566 $1,077,363 $517,922
14,548,351
kWh
$277,135
-
kW-mo/yr
$9,607 $(-300,604.0)
-
MMBtu
$(-1,494.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs