Assessment Year | 2015 |
---|---|
Principal Product | Dairy Products and Fruit Juice |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2026: Fluid Milk |
Sales Range | $100 M to 500M |
# of Employees | 183 |
Plant Area |
125,876
ft2
|
Annual Production | 449,857,161
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $582,465 | 15,321,000 |
kWh
|
$0.038 |
Electricity Demand | $354,643 | 32,839 |
kW-mo/yr
|
$10.80 |
Electricity Fees | $149,956 | - |
|
- |
Natural Gas | $250,638 | 54,961 |
MMBtu
|
$4.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $562,289 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $502,566 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $457,639 | $1,000,000 |
$496,236
13,939,200
kWh
|
$263,120
-
kW-mo/yr
|
- |
$(-301,717.0)
-
MMBtu
|
- | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $42,293 | - | - | - | $42,293 | - | - | |
03 | 2.3212: Optimize plant power factor | $9,011 | $8,260 | - | - | $9,011 | - | - | |
04 | 2.8114: Change rate schedules or other changes in utility service | $596 | - | - | - | $596 | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,582 | $51,370 |
$14,699
412,894
kWh
|
$13,042
-
kW-mo/yr
|
- | - | $(-3,159.0) | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,159 | $1,371 |
$322
9,044
kWh
|
$172
-
kW-mo/yr
|
- | - | $1,665 | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,050 | - |
$3,249
91,265
kWh
|
$801
-
kW-mo/yr
|
- | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $737 | $1,500 |
$737
20,690
kWh
|
- | - | - | - | |
09 | 2.4321: Upgrade obsolete equipment | $2,127 | $14,000 |
$2,127
59,758
kWh
|
- | - | - | - | |
10 | 2.4152: Use only certified motor repair shops | $2,199 | $1,865 |
$2,199
61,761
kWh
|
- | - | - | - | |
11 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $552 | - |
$552
15,500
kWh
|
- | - | - | - | |
12 | 2.2442: Preheat combustion air with waste heat | $7,205 | $18,400 | - | - | - |
$7,205
-
MMBtu
|
- | |
13 | 2.1222: Install turbulators | $8,026 | $9,000 | - | - | - |
$8,026
-
MMBtu
|
- | |
14 | 2.2123: Insulate feedwater tank | $1,113 | $862 | - | - | - |
$1,113
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $562,289 | $1,106,628 |
$520,121
14,610,112
kWh
|
$277,135
-
kW-mo/yr
|
$51,900 |
$(-285,373.0)
-
MMBtu
|
$(-1,494.0) | ||
TOTAL IMPLEMENTED | $502,566 | $1,077,363 |
$517,922
14,548,351
kWh
|
$277,135
-
kW-mo/yr
|
$9,607 |
$(-300,604.0)
-
MMBtu
|
$(-1,494.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs