Assessment Year | 1990 |
---|---|
Principal Product | INDUSTRIAL ADHESIVES |
NAICS |
n/a
|
SIC | 2891: Adhesives and Sealants |
Sales Range | $10 M to 50M |
# of Employees | 112 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 2,750
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $110,843 | 1,289,859 |
kWh
|
$0.086 |
Natural Gas | $78,483 | 20,186 |
MMBtu
|
$3.89 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,454 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,888 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.3132: Recharge batteries on during off-peak demand periods | $6,150 | $800 |
$6,150
-
kWh
|
- | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,481 | $500 | - |
$2,481
-
MMBtu
|
|
03 | 2.2414: Use waste heat from hot flue gases to preheat | $2,027 | $5,000 | - |
$2,027
-
MMBtu
|
|
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,539 | $800 | - |
$1,539
-
MMBtu
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $126 | $1,929 |
$126
1,465
kWh
|
- | |
06 | 2.2136: Install / repair insulation on steam lines | $249 | $53 | - |
$249
-
MMBtu
|
|
07 | 2.6121: Reduce hot water temperature to the minimum required | $882 | - |
$882
10,258
kWh
|
- | |
TOTAL RECOMMENDED | $13,454 | $9,082 |
$7,158
11,723
kWh
|
$6,296
-
MMBtu
|
||
TOTAL IMPLEMENTED | $9,888 | $3,282 |
$7,158
11,723
kWh
|
$2,730
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs