ITAC Assessment: UK1509
ITAC logo
ITAC Assessment: UK1509
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Casting Equipment and Machined Parts
NAICS 333249: Other Industrial Machinery Manufacturing
SIC 3559: Special Industry Machinery, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 58
Plant Area 57,600
ft2
Annual Production 12,529,411
lb
Production Hrs. Annual 6,240
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $167,248 2,203,200
kWh
Electricity Demand $37,423 5,226
kW-mo/yr
Electricity Fees $4,097 -
Natural Gas $72,584 8,505
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $50,586 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $36,304

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7135: Install occupancy sensors $1,084 $1,708 $1,084
14,278
kWh
- - - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,334 - $1,126
14,830
kWh
$208
-
kW-mo/yr
- - -
03 2.6124: Establish equipment maintenance schedule $218 - $525
6,920
kWh
$93
-
kW-mo/yr
- $(-400.0) -
04 2.6218: Turn off equipment when not in use $273 - $273
3,594
kWh
- - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,421 $1,200 $1,421
18,720
kWh
- - - -
06 2.4152: Use only certified motor repair shops $178 - $120
1,579
kWh
- - - $58
07 2.1233: Analyze flue gas for proper air/fuel ratio $5,118 $800 - - $5,118
-
MMBtu
- -
08 2.2442: Preheat combustion air with waste heat $3,869 $10,000 - - $3,869
-
MMBtu
- -
09 2.2437: Recover waste heat from equipment $9,895 $4,000 - - $9,895
-
MMBtu
- -
10 2.4239: Eliminate or reduce compressed air usage $5,561 $1,306 $4,616
60,818
kWh
$945
-
kW-mo/yr
- - -
11 2.4221: Install compressor air intakes in coolest locations $1,014 $1,858 $856
11,278
kWh
$158
-
kW-mo/yr
- - -
12 3.4155: Meter waste water $1,872 $464 - - - $1,872 -
13 2.7131: Add area lighting switches $3,010 $654 $3,010
39,936
kWh
- - - -
14 2.7142: Utilize higher efficiency lamps and/or ballasts $10,160 $18,174 $8,270
108,960
kWh
$1,890
-
kW-mo/yr
- - -
15 2.7442: Keep doors and windows shut when not on use $5,579 $4,086 - - $5,579
-
MMBtu
- -
TOTAL RECOMMENDED $50,586 $44,250 $21,301
280,913
kWh
$3,294
-
kW-mo/yr
$24,461
-
MMBtu
$1,472 $58
TOTAL IMPLEMENTED $36,304 $38,918 $10,044
132,331
kWh
$2,141
-
kW-mo/yr
$24,461
-
MMBtu
$(-400.0) $58
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs