Assessment Year | 2015 |
---|---|
Principal Product | Contract Packaging |
NAICS | 561910: Packaging and Labeling Services |
SIC | 7389: Business Services, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 55 |
Plant Area |
403,200
ft2
|
Annual Production | 338,100,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $171,119 | 2,394,720 |
kWh
|
$0.071 |
Electricity Demand | $34,982 | 5,227 |
kW-mo/yr
|
$6.69 |
Electricity Fees | $19,638 | - |
|
- |
Natural Gas | $228,226 | 28,964 |
MMBtu
|
$7.88 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $76,729 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $35,272 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2442: Preheat combustion air with waste heat | $8,833 | $6,030 | - | - |
$8,833
-
MMBtu
|
- | |
02 | 2.2442: Preheat combustion air with waste heat | $3,570 | $5,886 | - | - |
$3,570
-
MMBtu
|
- | |
03 | 2.2162: Reduce excess steam bleeding | $12,238 | $14,875 | - | - |
$12,238
-
MMBtu
|
- | |
04 | 2.2135: Repair and eliminate steam leaks | $18,785 | $5,847 | - | - |
$18,785
-
MMBtu
|
- | |
05 | 2.2136: Install / repair insulation on steam lines | $1,107 | $688 | - | - |
$1,107
-
MMBtu
|
- | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,452 | $1,000 | - | - |
$2,452
-
MMBtu
|
- | |
07 | 2.2531: Re-size charging openings or add movable cover or door | $7,973 | $112 |
$6,779
89,320
kWh
|
$1,194
-
kW-mo/yr
|
- | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $1,111 | $2,000 |
$941
12,396
kWh
|
$170
-
kW-mo/yr
|
- | - | |
09 | 2.4239: Eliminate or reduce compressed air usage | $7,513 | $841 |
$7,513
98,998
kWh
|
- | - | - | |
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,255 | - |
$1,255
16,541
kWh
|
- | - | - | |
11 | 2.4239: Eliminate or reduce compressed air usage | $1,642 | $1,284 |
$1,642
21,636
kWh
|
- | - | - | |
12 | 2.4224: Upgrade controls on compressors | $1,281 | $5,000 |
$1,082
14,257
kWh
|
$199
-
kW-mo/yr
|
- | - | |
13 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $829 | $1,200 |
$829
10,920
kWh
|
- | - | - | |
14 | 2.2437: Recover waste heat from equipment | $2,725 | $4,500 | - | - |
$2,725
-
MMBtu
|
- | |
15 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,531 | $2,478 |
$1,218
16,052
kWh
|
$313
-
kW-mo/yr
|
- | - | |
16 | 2.4321: Upgrade obsolete equipment | $1,481 | $2,501 |
$1,481
19,516
kWh
|
- | - | - | |
17 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $151 | - |
$151
1,999
kWh
|
- | - | - | |
18 | 2.4152: Use only certified motor repair shops | $2,252 | - |
$757
9,972
kWh
|
- | - | $1,495 | |
TOTAL RECOMMENDED | $76,729 | $54,242 |
$23,648
311,607
kWh
|
$1,876
-
kW-mo/yr
|
$49,710
-
MMBtu
|
$1,495 | ||
TOTAL IMPLEMENTED | $35,272 | $13,355 |
$11,120
146,537
kWh
|
$313
-
kW-mo/yr
|
$22,344
-
MMBtu
|
$1,495 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs