Assessment Year | 2025 |
---|---|
Principal Product | Turbine Blades |
NAICS | 333611: Turbine and Turbine Generator Set Units Manufacturing |
SIC | 3511: Steam, Gas, and Hydraulic Turbines, and Turbine Generator Set Units |
Sales Range | $50 M to 100M |
# of Employees | 80 |
Plant Area |
64,000
ft2
|
Annual Production | 180,000
units
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $127,767 | 2,872,479 |
kWh
|
$0.044 |
Electricity Demand | $178,672 | 9,709 |
kW-mo/yr
|
$18.40 |
Electricity Fees | $45,285 | - |
|
- |
Natural Gas | $13,317 | 779 |
MMBtu
|
$17.10 |
TOTAL YEARLY COSTS | $365,041 | |||
RECOMMENDED SAVINGS* | $192,439 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $45,516 | $322,608 |
$27,849
632,923
kWh
|
$17,667
-
kW-mo/yr
|
- | |
02 | 2.3191: Use demand controller or load shedder | $30,505 | $15,454 |
$12,639
287,248
kWh
|
$17,866
-
kW-mo/yr
|
- | |
03 | 2.6231: Utilize controls to operate equipment only when needed | $2,030 | $500 |
$2,030
46,141
kWh
|
- | - | |
04 | 2.2623: Minimize condenser cooling water temperature | $1,216 | $4,665 |
$1,216
27,641
kWh
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,201 | - |
$1,201
27,300
kWh
|
- | - | |
06 | 2.4224: Upgrade controls on compressors | $1,095 | $4,000 |
$1,095
24,879
kWh
|
- | - | |
07 | 4.424: Improve space comfort conditioning | $65,876 | $2,873 |
$(-1,211.0)
(-27,520)
kWh
|
$(-1,163.0)
-
kW-mo/yr
|
$68,250 | |
08 | 4.652: Replace existing equipment with more suitable substitutes | $45,000 | $1,900 | - | - | $45,000 | |
TOTAL RECOMMENDED | $192,439 | $352,000 |
$44,819
1,018,612
kWh
|
$34,370
-
kW-mo/yr
|
$113,250 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs