ITAC Assessment: UF0630
ITAC logo
ITAC Assessment: UF0630
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Asphalt
NAICS 324121: Asphalt Paving Mixture and Block Manufacturing
SIC 2951: Asphalt Paving Mixtures and Blocks
Sales Range $50
M
to 100
M
# of Employees 100
Plant Area 1,084,644
ft2
Annual Production 330,000
ton
Production Hrs. Annual 6,000
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $72,267 1,655,608
kWh
Electricity Demand $101,777 5,997
kW-mo/yr
Electricity Fees $4,463 -
Natural Gas $505,738 81,348
MMBtu
Waste Disposal Costs
Water Usage $16,280 1,237
Tgal
Water Disposal $7,008 737
Tgal
TOTAL YEARLY COSTS $707,533
RECOMMENDED SAVINGS* $155,222 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4224: Upgrade controls on compressors $66,329 $8,820 $(-525.0)
(-11,940)
kWh
$(-1,216.0)
-
kW-mo/yr
$68,070
-
MMBtu
- -
02 2.6126: Keep solid fuels / raw materials dry $25,034 $48,000 - - $25,034
-
MMBtu
- -
03 2.3191: Use demand controller or load shedder $12,224 $8,907 $5,099
115,893
kWh
$7,125
-
kW-mo/yr
- - -
04 2.1116: Improve combustion control capability $10,115 $2,000 - - $10,115
-
MMBtu
- -
05 2.1116: Improve combustion control capability $10,115 $40,000 - - $10,115
-
MMBtu
- -
06 2.4133: Use most efficient type of electric motors $9,264 $14,760 $2,418
54,916
kWh
$6,846
-
kW-mo/yr
- - -
07 2.6231: Utilize controls to operate equipment only when needed $6,407 $25,400 $6,407
145,608
kWh
- - - -
08 2.4112: Install soft-start to eliminate nuisance trips $1,256 $2,120 $1,256
28,535
kWh
- - - -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $958 - $715
16,264
kWh
- - $110 $133
10 2.6218: Turn off equipment when not in use $625 $1,750 $625
14,197
kWh
- - - -
11 4.661: Level zero – install control systems for existing equipment $11,572 $20,000 $1,457
33,112
kWh
- $10,115
-
MMBtu
- -
12 4.662: Level one – add communication using iiot devices to existing control system to modify operations $1,323 - $299
6,804
kWh
- $1,024
-
MMBtu
- -
TOTAL RECOMMENDED $155,222 $171,757 $17,751
403,389
kWh
$12,755
-
kW-mo/yr
$124,473
-
MMBtu
$110 $133
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs