| Assessment Year | 2025 |
|---|---|
| Principal Product | Asphalt |
| NAICS | 324121: Asphalt Paving Mixture and Block Manufacturing |
| SIC | 2951: Asphalt Paving Mixtures and Blocks |
| Sales Range | $50 M to 100M |
| # of Employees | 100 |
| Plant Area |
1,084,644
ft2
|
| Annual Production | 330,000
ton
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $72,267 | 1,655,608 |
kWh
|
$0.044 | |
| Electricity Demand | $101,777 | 5,997 |
kW-mo/yr
|
$16.97 | |
| Electricity Fees | $4,463 | - |
|
- | |
| Natural Gas | $505,738 | 81,348 |
MMBtu
|
$6.22 | |
| Waste Disposal Costs | |||||
| Water Usage | $16,280 | 1,237 |
Tgal
|
$13.16 | |
| Water Disposal | $7,008 | 737 |
Tgal
|
$9.51 | |
| TOTAL YEARLY COSTS | $707,533 | ||||
| RECOMMENDED SAVINGS* | $155,222 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4224: Upgrade controls on compressors | $66,329 | $8,820 |
$(-525.0)
(-11,940)
kWh
|
$(-1,216.0)
-
kW-mo/yr
|
$68,070
-
MMBtu
|
- | - | |
| 02 | 2.6126: Keep solid fuels / raw materials dry | $25,034 | $48,000 | - | - |
$25,034
-
MMBtu
|
- | - | |
| 03 | 2.3191: Use demand controller or load shedder | $12,224 | $8,907 |
$5,099
115,893
kWh
|
$7,125
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.1116: Improve combustion control capability | $10,115 | $2,000 | - | - |
$10,115
-
MMBtu
|
- | - | |
| 05 | 2.1116: Improve combustion control capability | $10,115 | $40,000 | - | - |
$10,115
-
MMBtu
|
- | - | |
| 06 | 2.4133: Use most efficient type of electric motors | $9,264 | $14,760 |
$2,418
54,916
kWh
|
$6,846
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.6231: Utilize controls to operate equipment only when needed | $6,407 | $25,400 |
$6,407
145,608
kWh
|
- | - | - | - | |
| 08 | 2.4112: Install soft-start to eliminate nuisance trips | $1,256 | $2,120 |
$1,256
28,535
kWh
|
- | - | - | - | |
| 09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $958 | - |
$715
16,264
kWh
|
- | - | $110 | $133 | |
| 10 | 2.6218: Turn off equipment when not in use | $625 | $1,750 |
$625
14,197
kWh
|
- | - | - | - | |
| 11 | 4.661: Level zero – install control systems for existing equipment | $11,572 | $20,000 |
$1,457
33,112
kWh
|
- |
$10,115
-
MMBtu
|
- | - | |
| 12 | 4.662: Level one – add communication using iiot devices to existing control system to modify operations | $1,323 | - |
$299
6,804
kWh
|
- |
$1,024
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $155,222 | $171,757 |
$17,751
403,389
kWh
|
$12,755
-
kW-mo/yr
|
$124,473
-
MMBtu
|
$110 | $133 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs