ITAC Assessment: UF0613
ITAC logo
ITAC Assessment: UF0613
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Plastic Containers
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 100
Plant Area 200,000
ft2
Annual Production 1,700,000,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $3,015,160 49,363,264
kWh
Electricity Demand $752,096 87,622
kW-mo/yr
Electricity Fees $383,259 -
TOTAL YEARLY COSTS $4,150,515
RECOMMENDED SAVINGS* $2,392,478 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.2623: Minimize condenser cooling water temperature $942,391 $22,400 $942,391
15,449,026
kWh
- - - -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $500,050 $518,990 $500,050
8,197,549
kWh
- - - -
03 2.3191: Use demand controller or load shedder $263,426 $265,574 $210,781
3,455,428
kWh
$52,645
-
kW-mo/yr
- - -
04 2.6231: Utilize controls to operate equipment only when needed $106,816 $25,400 $106,816
1,751,090
kWh
- - - -
05 2.4112: Install soft-start to eliminate nuisance trips $92,260 $61,871 $92,260
1,512,463
kWh
- - - -
06 2.9114: Use solar heat to make electricty $73,600 $322,608 $40,641
666,250
kWh
$32,959
-
kW-mo/yr
- - -
07 2.4224: Upgrade controls on compressors $47,434 - $47,434
777,600
kWh
- - - -
08 2.4133: Use most efficient type of electric motors $31,281 $10,800 $26,226
429,932
kWh
$5,055
-
kW-mo/yr
- - -
09 2.4321: Upgrade obsolete equipment $15,235 $68,900 $10,985
180,090
kWh
- - $4,250 -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $8,664 $22,804 $7,212
118,237
kWh
$1,452
-
kW-mo/yr
- - -
11 2.7141: Lower light fixtures in high ceiling areas $5,877 $6,200 $4,927
80,767
kWh
$950
-
kW-mo/yr
- - -
12 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,329 - $3,976
65,185
kWh
- $220 - $133
13 4.661: Level zero – install control systems for existing equipment $301,115 $60,000 $301,115
4,936,326
kWh
- - - -
TOTAL RECOMMENDED $2,392,478 $1,385,547 $2,294,814
37,619,943
kWh
$93,061
-
kW-mo/yr
$220 $4,250 $133
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs