Assessment Year | 2018 |
---|---|
Principal Product | Commercial Printing, Lithographic |
NAICS | 323111: Commercial Printing (except Screen and Books) |
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $10 M to 50M |
# of Employees | 277 |
Plant Area |
250,000
ft2
|
Annual Production | 183,205,000
units
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,061,709 | 18,660,660 |
kWh
|
$0.057 |
Electricity Demand | $422,211 | 34,523 |
kW-mo/yr
|
$12.23 |
Electricity Fees | $127,458 | - |
|
- |
Natural Gas | $169,522 | 44,884 |
MMBtu
|
$3.78 |
TOTAL YEARLY COSTS | $1,780,900 | |||
RECOMMENDED SAVINGS* | $87,021 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $37,619 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|
01 | 2.7233: Use properly designed and sized hvac equipment | $27,363 | $868 |
$27,363
480,060
kWh
|
- | |
02 | 2.3212: Optimize plant power factor | $17,618 | $30,000 | - | $17,618 | |
03 | 2.7226: Use computer programs to optimize hvac performance | $11,657 | $25,600 |
$11,657
204,506
kWh
|
- | |
04 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $8,569 | $45,225 |
$8,569
150,342
kWh
|
- | |
05 | 2.2522: Isolate hot or cold equipment | $6,694 | $2,710 |
$6,694
117,440
kWh
|
- | |
06 | 2.4224: Upgrade controls on compressors | $5,422 | $25,600 |
$5,422
95,115
kWh
|
- | |
07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $4,271 | $25,600 |
$4,271
74,922
kWh
|
- | |
08 | 2.4225: Install common header on compressors | $2,514 | $3,216 |
$2,514
44,100
kWh
|
- | |
09 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,687 | $1,850 |
$1,687
29,596
kWh
|
- | |
10 | 2.2611: Moderate cooling tower outlet temperature | $1,226 | $5,454 |
$1,226
21,520
kWh
|
- | |
TOTAL RECOMMENDED | $87,021 | $166,123 |
$69,403
1,217,601
kWh
|
$17,618 | ||
TOTAL IMPLEMENTED | $37,619 | $47,943 |
$37,619
659,998
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs