ITAC Assessment: UF0512
ITAC logo
ITAC Assessment: UF0512
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Iso-E, Geraniol, Pine Oil
NAICS 325199: All Other Basic Organic Chemical Manufacturing
SIC 2869: Industrial Organic Chemicals, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 89
Plant Area 1,100,000
ft2
Annual Production 22,274
ton
Production Hrs. Annual 8,736
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,161,881 21,324,017
kWh
Electricity Demand $237,928 34,810
kW-mo/yr
Electricity Fees $179,996 -
Natural Gas $2,228,418 456,062
MMBtu
Waste Disposal Costs
Water Usage $19,081 4,990
Tgal
Water Disposal $703,265 59,983
Tgal
TOTAL YEARLY COSTS $4,530,569
RECOMMENDED SAVINGS* $953,722 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $527,397

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Personnel Changes Savings Administrative Changes Savings By-product Production Savings
01 2.3416: Use combined cycle gas turbine generator sets with waste heat boilers connected to turbine exhaust $401,159 $2,500,000 $1,182,600
21,900,000
kWh
- $(-474,841.0)
-
MMBtu
- - $(-306,600.0) -
02 2.2522: Isolate hot or cold equipment $124,880 $17,000 $124,880
2,312,640
kWh
- - - - - -
03 2.3212: Optimize plant power factor $38,189 $13,000 $38,189
707,200
kWh
- - - - - -
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $23,030 $40,000 $23,030
426,480
kWh
- - - - - -
05 2.2112: Use correct size steam traps $27,893 $340 - - $27,893
-
MMBtu
- - - -
06 2.6231: Utilize controls to operate equipment only when needed $10,845 $2,750 $10,845
200,809
kWh
- - - - - -
07 2.2623: Minimize condenser cooling water temperature $26,348 $725 $26,348
487,582
kWh
- - - - - -
08 2.7243: Improve air circulation with destratification fans / other methods $9,636 $6,225 $4,324
80,066
kWh
$749
-
kW-mo/yr
- - $4,563 - -
09 2.2121: Increase amount of condensate returned $4,891 - - - $3,068
-
MMBtu
$1,823
-
Tgal
- - -
10 2.4225: Install common header on compressors $3,951 $11,185 $3,951
73,164
kWh
- - - - - -
11 2.4234: Cool compressor air intake with heat exchanger $2,136 $1,562 $2,136
39,560
kWh
- - - - - -
12 3.3128: Utilize other methods to remove contaminants $280,764 $300,000 - - - - - - $280,764
TOTAL RECOMMENDED $953,722 $2,892,787 $1,416,303
26,227,501
kWh
$749
-
kW-mo/yr
$(-443,880.0)
-
MMBtu
$1,823
-
Tgal
$4,563 $(-306,600.0) $280,764
TOTAL IMPLEMENTED $527,397 $351,225 $208,537
3,861,461
kWh
$749
-
kW-mo/yr
$30,961
-
MMBtu
$1,823
-
Tgal
$4,563 - $280,764
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Personnel Changes Savings Administrative Changes Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs