Assessment Year | 2011 |
---|---|
Principal Product | Baked goods |
NAICS | 311811: Retail Bakeries |
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $100 M to 500M |
# of Employees | 300 |
Plant Area |
320,517
ft2
|
Annual Production | 94,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,306,207 | 16,749,600 |
kWh
|
$0.078 |
Electricity Demand | $73,962 | 31,992 |
kW-mo/yr
|
$2.31 |
Natural Gas | $508,460 | 93,877 |
MMBtu
|
$5.42 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $142,146 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $56,768 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $34,948 | $19,732 |
$34,832
428,724
kWh
|
$116
-
kW-mo/yr
|
- | |
02 | 2.7135: Install occupancy sensors | $19,284 | $813 |
$19,284
246,118
kWh
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,401 | $404 |
$1,401
16,885
kWh
|
- | - | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $35,428 | $25,300 |
$35,428
454,212
kWh
|
- | - | |
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,135 | $1,000 |
$1,135
14,552
kWh
|
- | - | |
06 | 2.7496: Install partitions to reduce size of conditioned space | $1,175 | $4,385 |
$1,175
15,065
kWh
|
- | - | |
07 | 2.4112: Install soft-start to eliminate nuisance trips | $2,862 | $2,729 |
$2,862
34,479
kWh
|
- | - | |
08 | 2.7226: Use computer programs to optimize hvac performance | $14,978 | $39,066 |
$14,929
180,456
kWh
|
$49
-
kW-mo/yr
|
- | |
09 | 2.7124: Make a practice of turning off lights when not needed | $616 | - |
$616
7,907
kWh
|
- | - | |
10 | 2.7111: Reduce illumination to minimum necessary levels | $4,606 | $930 |
$4,606
59,055
kWh
|
- | - | |
11 | 2.2514: Cover open tanks | $9,431 | $2,321 | - | - |
$9,431
-
MMBtu
|
|
12 | 2.1222: Install turbulators | $16,282 | $7,500 | - | - |
$16,282
-
MMBtu
|
|
TOTAL RECOMMENDED | $142,146 | $104,180 |
$116,268
1,457,453
kWh
|
$164
-
kW-mo/yr
|
$25,713
-
MMBtu
|
||
TOTAL IMPLEMENTED | $56,768 | $21,949 |
$56,652
706,279
kWh
|
$116
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs