Assessment Year | 2008 |
---|---|
Principal Product | insolators and roofing |
NAICS | 326150: Urethane and Other Foam Product (except Polystyrene) Manufacturing |
SIC | 3086: Plastics Foam Products |
Sales Range | $10 M to 50M |
# of Employees | 140 |
Plant Area |
100,000
ft2
|
Annual Production | 100,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $538,997 | 5,783,782 |
kWh
|
$0.093 |
Natural Gas | $183,364 | 17,235 |
MMBtu
|
$10.64 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $146,787 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,050 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $662 | $300 |
$662
7,113
kWh
|
- | |
02 | 2.2441: Preheat boiler makeup water with waste process heat | $19,825 | $20,000 | - |
$19,825
-
MMBtu
|
|
03 | 2.4221: Install compressor air intakes in coolest locations | $7,271 | $400 |
$7,271
100,988
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $34,736 | $30,084 |
$34,736
541,032
kWh
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $666 | - |
$666
9,248
kWh
|
- | |
06 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $27,511 | $182,894 |
$27,511
256,683
kWh
|
- | |
07 | 2.4151: Develop a repair/replace policy | $648 | - |
$648
6,720
kWh
|
- | |
08 | 2.4225: Install common header on compressors | $6,290 | $550 |
$6,290
87,360
kWh
|
- | |
09 | 2.7243: Improve air circulation with destratification fans / other methods | $49,178 | $49,400 |
$49,178
553,225
kWh
|
- | |
TOTAL RECOMMENDED | $146,787 | $283,628 |
$126,962
1,562,369
kWh
|
$19,825
-
MMBtu
|
||
TOTAL IMPLEMENTED | $36,050 | $30,084 |
$36,050
557,000
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs