ITAC Assessment: UF0388
ITAC logo
ITAC Assessment: UF0388
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Fruit Juice
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range n/a
# of Employees 64
Plant Area 81,000
ft2
Annual Production 100
Tgal
Production Hrs. Annual 2,210
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $428,133 5,728,380
kWh
Electricity Demand $45,122 24,224
kW-mo/yr
Natural Gas $110,013 10,019
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $38,794 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,746 $4,846 $5,725
73,280
kWh
$21
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,378 $1,688 $4,374
17,148
kWh
$4
-
kW-mo/yr
-
03 2.7135: Install occupancy sensors $341 $342 $341
4,544
kWh
- -
04 2.7111: Reduce illumination to minimum necessary levels $922 $2,346 $922
12,287
kWh
- -
05 2.2136: Install / repair insulation on steam lines $7,286 $1,238 - - $7,286
-
MMBtu
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,957 - $1,957
22,045
kWh
- -
07 2.2136: Install / repair insulation on steam lines $193 $374 - - $193
-
MMBtu
08 2.6231: Utilize controls to operate equipment only when needed $1,088 $93 $1,088
11,508
kWh
- -
09 2.4221: Install compressor air intakes in coolest locations $3,663 $1,320 $3,663
48,846
kWh
- -
10 2.7134: Use photocell controls $553 $240 $546
6,334
kWh
$7
-
kW-mo/yr
-
11 2.2442: Preheat combustion air with waste heat $12,667 $65,000 - - $12,667
-
MMBtu
TOTAL RECOMMENDED $38,794 $77,487 $18,616
195,992
kWh
$32
-
kW-mo/yr
$20,146
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs