| Assessment Year | 2004 |
|---|---|
| Principal Product | Weekly Publications |
| NAICS | 323111: Commercial Printing (except Screen and Books) |
| SIC | 2759: Commercial Printing, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 230 |
| Plant Area |
69,000
ft2
|
| Annual Production | 42,640,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $131,633 | 2,638,262 |
kWh
|
$0.050 |
| Electricity Demand | $42,504 | 6,198 |
kW-mo/yr
|
$6.86 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $33,289 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $20,307 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.6125: Keep equipment clean | $1,555 | $432 |
$1,555
29,912
kWh
|
- | - | - | - | |
| 02 | 2.7131: Add area lighting switches | $8,786 | $400 |
$8,786
127,332
kWh
|
- | - | - | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,468 | - |
$1,468
21,273
kWh
|
- | - | - | - | |
| 04 | 2.7135: Install occupancy sensors | $1,509 | $1,035 |
$1,509
21,869
kWh
|
- | - | - | - | |
| 05 | 4.111: Add equipment/ operators to reduce production bottleneck | $1,651 | $5,000 |
$699
13,441
kWh
|
$952
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,482 | $252 |
$3,482
50,471
kWh
|
- | - | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,554 | $5,600 |
$2,103
40,443
kWh
|
$451
-
kW-mo/yr
|
- | - | - | |
| 08 | 2.4151: Develop a repair/replace policy | $1,159 | $5,189 |
$835
16,049
kWh
|
$324
-
kW-mo/yr
|
- | - | - | |
| 09 | 2.8112: Combine utility meters | $1,189 | - | - | - | $1,189 | - | - | |
| 10 | 3.4155: Meter waste water | $1,036 | $940 | - | - | - |
$1,036
-
Tgal
|
- | |
| 11 | 4.711: Initiate a total quality management program | $8,900 | $2,070 | - | - | - | - | $8,900 | |
| TOTAL RECOMMENDED | $33,289 | $20,918 |
$20,437
320,790
kWh
|
$1,727
-
kW-mo/yr
|
$1,189 |
$1,036
-
Tgal
|
$8,900 | ||
| TOTAL IMPLEMENTED | $20,307 | $13,543 |
$9,443
158,148
kWh
|
$775
-
kW-mo/yr
|
$1,189 | - | $8,900 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs