Assessment Year | 2023 |
---|---|
Principal Product | Metal Fabrication |
NAICS | 332322: Sheet Metal Work Manufacturing |
SIC | 3444: Sheet Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
80,000
ft2
|
Annual Production | 906,884
units
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $103,869 | 1,375,200 |
kWh
|
$0.076 | |
Electricity Demand | $47,638 | 4,589 |
kW-mo/yr
|
$10.38 | |
Electricity Fees | $15,858 | - |
|
- | |
Natural Gas | $9,205 | 986 |
MMBtu
|
$9.34 | |
Waste Disposal Costs | |||||
Water Usage | $1,414 | 233 |
Tgal
|
$6.08 | |
Water Disposal | $1,299 | 233 |
Tgal
|
$5.58 | |
Other Liquid (non-haz) | $5,802 | 1 |
gal
|
$5,802.00 | |
TOTAL YEARLY COSTS | $185,085 | ||||
RECOMMENDED SAVINGS* | $14,708 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $1,629 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4313: Provide proper maintenance of motor driven equipment | $529 | - |
$529
7,004
kWh
|
- | - | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $425 | - |
$256
3,388
kWh
|
$169
-
kW-mo/yr
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,164 | - |
$2,663
35,264
kWh
|
$501
-
kW-mo/yr
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,629 | $100 |
$1,371
18,153
kWh
|
$258
-
kW-mo/yr
|
- | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $1,431 | $994 |
$1,431
18,951
kWh
|
- | - | - | |
06 | 2.7135: Install occupancy sensors | $7,530 | $4,236 |
$6,567
86,981
kWh
|
- | $178 | $785 | |
TOTAL RECOMMENDED | $14,708 | $5,330 |
$12,817
169,741
kWh
|
$928
-
kW-mo/yr
|
$178 | $785 | ||
TOTAL IMPLEMENTED | $1,629 | $100 |
$1,371
18,153
kWh
|
$258
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs