Assessment Year | 2002 |
---|---|
Principal Product | Carbonated Soft Drinks |
NAICS |
n/a
|
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
280,000
ft2
|
Annual Production | 22,000,000
pieces
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $269,706 | 7,257,694 |
kWh
|
$0.037 |
Electricity Demand | $130,518 | 17,484 |
kW-mo/yr
|
$7.46 |
Natural Gas | $198,743 | 20,590 |
MMBtu
|
$9.65 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $490,172 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,243 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Primary Raw Material Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $19,418 | $9,500 |
$18,075
488,527
kWh
|
$1,343
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $14,245 | $30,089 |
$9,796
264,757
kWh
|
$4,449
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,874 | - |
$2,874
47,901
kWh
|
- | - | - | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $912 | $2,000 |
$912
15,207
kWh
|
- | - | - | - | - | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $6,811 | $20,000 |
$6,811
113,517
kWh
|
- | - | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,022 | $1,000 |
$3,135
52,256
kWh
|
- | - | $(-113.0) | - | - | |
07 | 2.9112: Use solar heat to heat water | $149,057 | $2,450,000 | - | - |
$149,057
-
MMBtu
|
- | - | - | |
08 | 2.3212: Optimize plant power factor | $3,750 | $5,000 | - | - | - | - | - | $3,750 | |
09 | 2.8121: Apply for tax-free status for energy purchases | $18,976 | $50 | - | - | - | - | - | $18,976 | |
10 | 3.5311: Recover and reuse waste material | $265,592 | $500,000 | - | - | - | - | $265,592 | - | |
11 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $1,014 | - | - | - | - | $1,014 | - | - | |
12 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,501 | - |
$4,501
75,132
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $490,172 | $3,017,639 |
$46,104
1,057,297
kWh
|
$5,792
-
kW-mo/yr
|
$149,057
-
MMBtu
|
$901 | $265,592 | $22,726 | ||
TOTAL IMPLEMENTED | $36,243 | $31,139 |
$12,931
317,013
kWh
|
$4,449
-
kW-mo/yr
|
- | $(-113.0) | - | $18,976 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Primary Raw Material Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs