Assessment Year | 2001 |
---|---|
Principal Product | Cookies |
NAICS |
n/a
|
SIC | 2052: Cookies and Crackers |
Sales Range | n/a |
# of Employees | 200 |
Plant Area |
68,500
ft2
|
Annual Production | 4,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $140,132 | 3,156,320 |
kWh
|
$0.044 |
Electricity Demand | $47,669 | 6,575 |
kW-mo/yr
|
$7.25 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $950,818 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $205,913 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,662 | $6,465 |
$4,540
103,172
kWh
|
$1,122
-
kW-mo/yr
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,358 | $500 |
$4,418
61,355
kWh
|
- | $(-60.0) | - | - | |
03 | 2.6231: Utilize controls to operate equipment only when needed | $18,443 | $30,000 |
$18,443
419,159
kWh
|
- | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,155 | - |
$3,155
43,825
kWh
|
- | - | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $800 | $2,000 |
$800
11,119
kWh
|
- | - | - | - | |
06 | 4.522: Modify storage space to avoid rental of a warehouse | $720,000 | $559,440 | - | - | - | $720,000 | - | |
07 | 4.711: Initiate a total quality management program | $169,000 | $176,000 | - | - | - | - | $169,000 | |
08 | 4.651: Install back-up equipment | $29,400 | $64,000 | - | - | - | - | $29,400 | |
TOTAL RECOMMENDED | $950,818 | $838,405 |
$31,356
638,630
kWh
|
$1,122
-
kW-mo/yr
|
$(-60.0) | $720,000 | $198,400 | ||
TOTAL IMPLEMENTED | $205,913 | $240,500 |
$7,573
105,180
kWh
|
- | $(-60.0) | - | $198,400 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs