ITAC Assessment: UF0277
ITAC logo
ITAC Assessment: UF0277
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product MultiWall Paper Shipping Bags
NAICS
n/a
SIC 2674: Uncoated Paper and Multiwall Bags
Sales Range $50
M
to 100
M
# of Employees 325
Plant Area 174,000
ft2
Annual Production 180,000,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $191,704 8,970,172
kWh
Electricity Demand $146,263 15,880
kW-mo/yr
Electricity Fees $9,184 -
Natural Gas $89,909 8,234
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $650,050 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,315

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,104 - $10,140
252,593
kWh
- - - $(-36.0) -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $5,130 - $3,052
145,336
kWh
$2,078
-
kW-mo/yr
- - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,261 - $232
11,038
kWh
$139
-
kW-mo/yr
- - - $890
04 2.7145: Install skylights $20,383 - $7,705
366,912
kWh
$12,378
-
kW-mo/yr
- - $300 -
05 4.652: Replace existing equipment with more suitable substitutes $2,497 - $1,872
89,166
kWh
- - - - $625
06 2.7226: Use computer programs to optimize hvac performance $15,737 - $15,737
749,381
kWh
- - - - -
07 2.7141: Lower light fixtures in high ceiling areas $14,700 - $9,183
437,300
kWh
$5,517
-
kW-mo/yr
- - - -
08 2.4151: Develop a repair/replace policy $8,088 - $5,049
240,408
kWh
$3,039
-
kW-mo/yr
- - - -
09 2.4231: Reduce the pressure of compressed air to the minimum required $3,962 - $3,962
99,056
kWh
- - - - -
10 2.7135: Install occupancy sensors $1,315 - $1,315
62,596
kWh
- - - - -
11 2.2113: Repair or replace steam traps $2,712 - - - $2,712
-
MMBtu
- - -
12 3.1191: Change procedures / equipment / operating conditions $9,600 - - - - $9,600
-
lb
- -
13 2.4223: Install direct acting units in place of compressed air pressure system in safety system $7,281 - $7,281
194,375
kWh
- - - - -
14 4.441: Install automatic packing equipment $7,280 - - - - - $7,280 -
15 2.7491: Insulate glazing, walls, ceilings, and roofs $540,000 - - - - - $540,000 -
TOTAL RECOMMENDED $650,050 - $65,528
2,648,161
kWh
$23,151
-
kW-mo/yr
$2,712
-
MMBtu
$9,600
-
lb
$547,544 $1,515
TOTAL IMPLEMENTED $33,315 - $25,522
832,712
kWh
$5,117
-
kW-mo/yr
$2,712
-
MMBtu
- $(-36.0) -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs