| Assessment Year | 2001 |
|---|---|
| Principal Product | MultiWall Paper Shipping Bags |
| NAICS |
n/a
|
| SIC | 2674: Uncoated Paper and Multiwall Bags |
| Sales Range | $50 M to 100M |
| # of Employees | 325 |
| Plant Area |
174,000
ft2
|
| Annual Production | 180,000,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $191,704 | 8,970,172 |
kWh
|
$0.021 |
| Electricity Demand | $146,263 | 15,880 |
kW-mo/yr
|
$9.21 |
| Electricity Fees | $9,184 | - |
|
- |
| Natural Gas | $89,909 | 8,234 |
MMBtu
|
$10.92 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $650,050 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $33,315 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,104 | - |
$10,140
252,593
kWh
|
- | - | - | $(-36.0) | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,130 | - |
$3,052
145,336
kWh
|
$2,078
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,261 | - |
$232
11,038
kWh
|
$139
-
kW-mo/yr
|
- | - | - | $890 | |
| 04 | 2.7145: Install skylights | $20,383 | - |
$7,705
366,912
kWh
|
$12,378
-
kW-mo/yr
|
- | - | $300 | - | |
| 05 | 4.652: Replace existing equipment with more suitable substitutes | $2,497 | - |
$1,872
89,166
kWh
|
- | - | - | - | $625 | |
| 06 | 2.7226: Use computer programs to optimize hvac performance | $15,737 | - |
$15,737
749,381
kWh
|
- | - | - | - | - | |
| 07 | 2.7141: Lower light fixtures in high ceiling areas | $14,700 | - |
$9,183
437,300
kWh
|
$5,517
-
kW-mo/yr
|
- | - | - | - | |
| 08 | 2.4151: Develop a repair/replace policy | $8,088 | - |
$5,049
240,408
kWh
|
$3,039
-
kW-mo/yr
|
- | - | - | - | |
| 09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,962 | - |
$3,962
99,056
kWh
|
- | - | - | - | - | |
| 10 | 2.7135: Install occupancy sensors | $1,315 | - |
$1,315
62,596
kWh
|
- | - | - | - | - | |
| 11 | 2.2113: Repair or replace steam traps | $2,712 | - | - | - |
$2,712
-
MMBtu
|
- | - | - | |
| 12 | 3.1191: Change procedures / equipment / operating conditions | $9,600 | - | - | - | - |
$9,600
-
lb
|
- | - | |
| 13 | 2.4223: Install direct acting units in place of compressed air pressure system in safety system | $7,281 | - |
$7,281
194,375
kWh
|
- | - | - | - | - | |
| 14 | 4.441: Install automatic packing equipment | $7,280 | - | - | - | - | - | $7,280 | - | |
| 15 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $540,000 | - | - | - | - | - | $540,000 | - | |
| TOTAL RECOMMENDED | $650,050 | - |
$65,528
2,648,161
kWh
|
$23,151
-
kW-mo/yr
|
$2,712
-
MMBtu
|
$9,600
-
lb
|
$547,544 | $1,515 | ||
| TOTAL IMPLEMENTED | $33,315 | - |
$25,522
832,712
kWh
|
$5,117
-
kW-mo/yr
|
$2,712
-
MMBtu
|
- | $(-36.0) | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs