| Assessment Year | 2026 |
|---|---|
| Principal Product | municipal administration |
| NAICS | 921190: Other General Government Support |
| SIC | 8741: Management Services |
| Sales Range | less than $500 k |
| # of Employees | 20 |
| Plant Area |
58,333
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $48,706 | 335,778 |
kWh
|
$0.15 | |
| Natural Gas | $19,505 | 2,185 |
MMBtu
|
$8.93 | |
| Waste Disposal Costs | |||||
| Water Usage | $2,160 | 180 |
Tgal
|
$12.00 | |
| TOTAL YEARLY COSTS | $70,371 | ||||
| RECOMMENDED SAVINGS* | $54,979 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $4,633 | $6,500 |
$1,482
10,216
kWh
|
$3,151
-
MMBtu
|
|
| 02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,582 | $700 |
$63
435
kWh
|
$1,519
-
MMBtu
|
|
| 03 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $131 | $3,000 | - |
$131
-
MMBtu
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,349 | $5,000 |
$3,349
23,088
kWh
|
- | |
| 05 | 2.9114: Use solar heat to make electricty | $45,284 | $450,000 |
$45,284
312,190
kWh
|
- | |
| TOTAL RECOMMENDED | $54,979 | $465,200 |
$50,178
345,929
kWh
|
$4,801
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs