Assessment Year | 2017 |
---|---|
Principal Product | Bottled Liquor |
NAICS | 312140: Distilleries |
SIC | 2085: Distilled and Blended Liquors |
Sales Range | $10 M to 50M |
# of Employees | 45 |
Plant Area |
110,000
ft2
|
Annual Production | 800,000
units
|
Production Hrs. Annual | 2,063
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $51,851 | 380,259 |
kWh
|
$0.14 | |
Electricity Demand | $10,895 | 1,548 |
kW-mo/yr
|
$7.04 | |
Electricity Fees | $720 | - |
|
- | |
Natural Gas | $54,839 | 10,055 |
MMBtu
|
$5.45 | |
Waste Disposal Costs | |||||
Water Usage | $11,220 | 2,703 |
Tgal
|
$4.15 | |
Water Disposal | $25,763 | 1,801 |
Tgal
|
$14.31 | |
TOTAL YEARLY COSTS | $155,288 | ||||
RECOMMENDED SAVINGS* | $24,748 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $19,451 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.8112: Combine utility meters | $1,370 | - | - | - | $1,370 | - | |
02 | 2.7224: Reduce space conditioning during non-working hours | $5,897 | - | - | - | - |
$5,897
-
MMBtu
|
|
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,800 | $3,250 | - | - | - |
$2,800
-
MMBtu
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,266 | $7,210 |
$7,622
55,851
kWh
|
$1,644
-
kW-mo/yr
|
- | - | |
05 | 2.7134: Use photocell controls | $3,473 | $1,550 |
$3,473
25,449
kWh
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,488 | $300 |
$1,111
8,141
kWh
|
$377
-
kW-mo/yr
|
- | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $454 | $1,400 |
$339
2,484
kWh
|
$115
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $24,748 | $13,710 |
$12,545
91,925
kWh
|
$2,136
-
kW-mo/yr
|
$1,370 |
$8,697
-
MMBtu
|
||
TOTAL IMPLEMENTED | $19,451 | $10,760 |
$8,733
63,992
kWh
|
$2,021
-
kW-mo/yr
|
- |
$8,697
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs