Assessment Year | 2015 |
---|---|
Principal Product | Glass Tubes |
NAICS | 327212: Other Pressed and Blown Glass and Glassware Manufacturing |
SIC | 3229: Pressed and Blown Glass and Glassware, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 88 |
Plant Area |
250,000
ft2
|
Annual Production | 129,518,000
pieces
|
Production Hrs. Annual | 8,232
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $801,583 | 11,248,800 |
kWh
|
$0.071 |
Electricity Demand | $86,297 | 18,540 |
kW-mo/yr
|
$4.65 |
Natural Gas | $273,646 | 63,936 |
MMBtu
|
$4.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $169,645 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $24,296 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,241 | $50 |
$2,324
33,869
kWh
|
$240
-
kW-mo/yr
|
- | - | - | $677 | |
02 | 2.6231: Utilize controls to operate equipment only when needed | $243 | $400 |
$220
3,489
kWh
|
$23
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.2515: Use optimum thickness insulation | $28,993 | $2,000 | - | - | - |
$28,993
-
MMBtu
|
- | - | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $4,909 | $10,000 | - | - | - |
$4,909
-
MMBtu
|
- | - | |
05 | 2.2511: Insulate bare equipment | $4,777 | $600 | - | - | - |
$4,777
-
MMBtu
|
- | - | |
06 | 2.4131: Size electric motors for peak operating efficiency | $1,021 | $400 |
$752
10,962
kWh
|
$50
-
kW-mo/yr
|
- | - | - | $219 | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $14,734 | - |
$10,565
153,945
kWh
|
$1,090
-
kW-mo/yr
|
- | - | - | $3,079 | |
08 | 2.4151: Develop a repair/replace policy | $5,978 | $19,581 |
$5,418
78,955
kWh
|
$560
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.8112: Combine utility meters | $105,406 | $156,400 | - | - | $105,406 | - | - | - | |
10 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $343 | - | - | - | - | - | $343 | - | |
TOTAL RECOMMENDED | $169,645 | $189,431 |
$19,279
281,220
kWh
|
$1,963
-
kW-mo/yr
|
$105,406 |
$38,679
-
MMBtu
|
$343 | $3,975 | ||
TOTAL IMPLEMENTED | $24,296 | $19,631 |
$18,307
266,769
kWh
|
$1,890
-
kW-mo/yr
|
- | - | $343 | $3,756 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs