Assessment Year | 2015 |
---|---|
Principal Product | Automotive Components |
NAICS | 336370: Motor Vehicle Metal Stamping |
SIC | 3465: Automotive Stampings |
Sales Range | $10 M to 50M |
# of Employees | 185 |
Plant Area |
172,000
ft2
|
Annual Production | 5,500,000
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $305,917 | 4,260,706 |
kWh
|
$0.072 |
Electricity Demand | $58,270 | 12,232 |
kW-mo/yr
|
$4.76 |
Natural Gas | $32,641 | 3,369 |
MMBtu
|
$9.69 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $135,330 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,454 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8112: Combine utility meters | $13,359 | - | - | - | $13,359 | - | - | - | |
02 | 2.3134: Shift from daytime to nighttime operation | $1,749 | - | - |
$1,749
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4224: Upgrade controls on compressors | $3,626 | $200 |
$3,179
42,000
kWh
|
$447
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7224: Reduce space conditioning during non-working hours | $3,654 | $600 |
$107
1,411
kWh
|
- | - |
$3,547
-
MMBtu
|
- | - | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $2,374 | - |
$2,374
31,359
kWh
|
- | - | - | - | - | |
06 | 2.6212: Turn off equipment during breaks, reduce operating time | $47,012 | - |
$41,219
544,500
kWh
|
$5,793
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $21,116 | - |
$18,514
244,565
kWh
|
$2,602
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,293 | $25,800 |
$8,228
108,696
kWh
|
$2,065
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,453 | $20,680 |
$11,263
148,790
kWh
|
$1,583
-
kW-mo/yr
|
- | - | $607 | - | |
10 | 2.7135: Install occupancy sensors | $1,355 | $3,835 |
$1,088
14,377
kWh
|
$153
-
kW-mo/yr
|
- | - | $114 | - | |
11 | 3.5316: Contract a wood pallet recycling company | $11,244 | - | - | - | - | - | - | $11,244 | |
12 | 3.8211: Convert to aqueous cleaning system | $6,095 | $7,375 | - | - | - | - | - | $6,095 | |
TOTAL RECOMMENDED | $135,330 | $58,490 |
$85,972
1,135,698
kWh
|
$14,392
-
kW-mo/yr
|
$13,359 |
$3,547
-
MMBtu
|
$721 | $17,339 | ||
TOTAL IMPLEMENTED | $19,454 | $7,375 | - | - | $13,359 | - | - | $6,095 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs